APPRAISALS OF ENVIRONMENTAL PERFORMANCE AT RANGER AND THE OLYMPIC DAM
OPERATION
Ranger
The most impotent appraisal of environmental performance at Ranger was
provided by the Supervising Scientist, Mr Barry Carbon, in a submission
to the Committee. On key points the Supervising Scientist found that:
- There has been no deleterious effect on the local river system from
activities at Ranger. (S 85, Attachment A, 16)
- The Ranger tailings storage system has operated satisfactorily in
containing the tailings, and it has caused no environmental degradation.
A final decision has [not] yet been made on the long term management
of tailings. The E[nvironmental] R[equirements] provide for final placement
of the tailings below grade unless an alternative is approved by Supervising
Scientist and the N[orthern] L[and] C[ouncil]. A collaborative research
program has been agreed between ERISS and ERA to resolve the issue of
final tailings disposal. There is also a commitment for in pit disposal
of Orebody #3 tailings into the exhausted No 1 pit. (S 85, Attachment
A, 16)
- Seepage from the tailings dam was overestimated by the RUEI [Fox inquiry],
as were the transport of heavy metals in groundwater and the environmentally
vitiating effects of seepage. No environmental effects are observable.
A management regime was able to be developed to allow performance well
within the expectations outlined by the inquiry." (S 85, Attachment
A, 16)
- The [Fox] Commission's concerns over the potential for damage caused
by blasting have been proved to be unfounded. A management regime was
able to be developed to allow performance well within the expectations
outlined by the RUEI. (Attachment A, 16)
- The negative effects on the environment by both sulfur dioxide and
radon were over estimated by the [Fox] Commission. These pollutants
are effectively undetectable in the broader environment. (S 85, Attachment
A, 16)
The control regime for the Ranger mine requires that incidents of various
types must be reported to the Supervising Scientist. These incidents are
in turn recorded in the annual reports of the Supervising Scientist. A
consolidated list is to be found at Appendix 2.9.
Mr Barry Carbon, the Supervising Scientist, informed the Committee:
The table . . . shows that throughout the life of the Ranger
mine there have been several incidents and infringements which have
at times breached the Environmental Requirements and most have had the
potential to cause some degree of adverse environmental impact. The
Supervising Scientist, and his staff, have investigated every such incident
reported by Ranger and, with two exceptions, have concluded that there
has been no significant environmental impact at the time of the incident
nor has there been any lasting environmental detriment. The two exceptions
are the incident of 5 July 1982 which involved the health and safety
of two workers in the packing plant.The Supervising Scientist undertook
a special study of radiation safety standards at Ranger after the incident
which was the subject of a special report to the Commonwealth Minister
on 11 November 1983.
The Supervising Scientist concluded that there were areas of
radiation protection procedures at Ranger which could be improved but
despite some reservations about training he did assess that radiation
exposures of workers during routine operations were likely to have been
below the appropriate regulatory dose limit. Since the time of the incident
and subsequent reports by the Supervising Scientist and the NT Department
of Health substantial improvements have been made by ERA in standards
of radiation protection and training.
The second incident was the unacceptable environmental impact
arising from the diesel spill of 6 December 1995. The Supervising Scientist
is of the opinion that this is the first unacceptable and lasting environmental
impact that has arisen as a consequence of operations at Ranger. The
Company have since revised procedures to ensure that the incident should
not be capable of being repeated. The company has also commissioned
an independent audit of fuel and similar hazard management on site and
implemented almost all of the recommendations from the audit report.
Since the creation of the office the Supervising Scientist has
reported annually to Parliament on the level and standards of environmental
protection being achieved in the Alligator Rivers Region. Despite the
incidents reported this annual report has consistently commented that
the Supervising Scientist is of the opinion that there are no lasting
environmental impacts as a consequence of the operation of the uranium
mine that can be detected away from the mining lease. This is an indication
of the success that has been achieved as a result of the implementation
of the regulatory regime and environmental protection procedures throughout
the Alligator Rivers Region. (S 85, Attachment B, Section 3)
Several observers challenged the conclusions of the Supervising Scientist,
often in general terms without additional evidence.
The Australian Conservation Foundation also referred to a list of incidents
and events at Ranger which they consider "indicate a quite different
picture" to a view that " Ranger has an excellent environmental
record"(S 81,1.1.1,2).The ACF observed:
It is maintained by ERA and more recently the OSS that most of
these authorised or accidental releases have had no significant impact
on the environment. Nonetheless it is clear that contaminated water
is either intentionally or accidentally entering the surrounding wetlands.
The dumping of industrial and radioactive wastes into a World Heritage
area is inappropriate and contrary to the values of a World Heritage
area.(S 81, 1.1.1,2).
Everyone for a NUclear Free Future made a submission to the Committee
which stated:
The Ranger mine has a long history of accidental and intentional
releases of contaminated water. Initial unrealistic expectations
led to planning faults and Energy Resources of Australia (ERA) have
struggled with water problems all the way. Much more research is necessary
before we can be reasonably assured that ERA's activities will not be
detrimental to the ecological integrity of Kakadu National Park.(S 93,
4)
ERA's achievement at Ranger is a consequence of a framework embracing
the mine's own environmental staff and the research and investigations
conducted by or under the auspices of the Supervising Scientist, especially
the Environmental Research Institute of the Supervising Scientist. ERA's
own active and enterprising environment policy is supported by a staff
of 32, including a Labrador (S63, 5). In 1995-6, Ranger had approved research
projects totalling $1.4 million and involving 7 institutions including
CSIRO, ANSTO, ANCA, ERISS and Newcastle University.
Ranger's current environmental activities include enhanced tailings management
practices, particularly design of appropriate capping systems which ensure
cost-effective construction, optimal consolidation of tailings deposits
and stability of the final landform and technologies for effective consolidation
of tailings deposits; development of various technologies relating to
stockpiles; and strategies for effective management of natural processes
in the Magela Creek catchment, especially knowledge of wetland processes
in natural and constructed waterbodies in terms of contaminant movement
and impact on water quality and ecosystem diversity, and design principles
for construction of small and large scale wetland filters that are compatible
with natural wetland processes. (S 63, 30)
The Committee especially noted the view contained in one submission generally
critical of the mines: ". . . Ranger . . . is certinly [sic] run
safer than most mines" (Matthew Elliott, Uranium Research Group,
letter of 28 July 1996).
In appraising performance of the Ranger mine in environmental matters,
the Committee gave particular attention to the counsel of the Supervising
Scientist that:
The operation of any mine cannot be conducted without there being
impact on the environment. The environment on the mine lease itself
is certainly disturbed but the objective of any environmental protection
regime is that there be minimal impact off-site and that this impact
is within standards that are set to ensure a high level of environmental
protection.
The data that have been collected in a rigorous monitoring program
at Ranger have shown that throughout the life of the mine no harm has
come to the aquatic ecosystems downstream from Ranger and that people
living in the region have been protected(S 85, Attachment B Conclusion).
The Supervising Scientist concluded his appraisal of Ranger: "The
co-existence of a uranium mine with a major national park for over 16
years, with no adverse impacts on the ecological integrity of the park,
has to be considered a notable achievement." (S 85, Attachment A,
17)
Olympic Dam Operation
Continuing environmental management at the Olympic Dam Operation is governed
by clause 11 of the Indenture Agreement. Clause 11 requires that a programme
for the protection, management and rehabilitation (if appropriate) of
the environment, including arrangements for monitoring and studying sample
areas in order to ascertain the effectiveness of such a programme be submitted
to the Minister every three years. Current programmes are set out in the
Environmental Management and Monitoring Plan 1996. Monthly, quarterly
and annual reports are submitted to State Government authorities. Annual
reports are available publicly.
The management programme covers vegetation, drill pad rehabilitation,
fauna, soil salinity, hydrogeology, airborne emissions and solid wastes,
and wellfields.
The most substantial public review so far of environmental management
at the Olympic Dam Operation was conducted by the Environment, Resources
and Development Committee of the South Australian Parliament. In its Nineteenth
report of 10 April 1996 the ERD Committee examined "a massive leakage
of water at Roxby Downs "(term of reference II.(a)).
Crucial findings of the ERD Committee were:
- the Olympic Dam tailings retention system did not receive the degree
of informed supervision of its various components it required to operate
efficiently as designed and that this inadequate supervision by the
operators of the tailings retention system, particularly the system
as extended in 1991, contributed to the massive leakage from it.(p 5)
- although admitting difficulties of interpretation, the operators were
reluctant to accept that a leakage from the tailings retention system
was occuring [sic], despite mounting evidence to that effect.
- confident of the benign impact of any seepage, the operators were
reluctant to admit deficiencies in the design and difficulties with
the operation of the tailings retention system which were contributing
to the leakage from it and that this reluctance coloured their reporting
of operations at Olympic Dam and delayed measures necessary to understand
the leakage and reduce its impact.
- it was only when the leakage was too big to ignore or to explain away
and only in response to hard prompting from regulatory agencies that
ad hoc operational changes were converted into radical remedial action
to alter the original defective design concept.
- the monitoring systems designed in part to detect leakage from the
Olympic Dam tailings retention system were defective but that, following
prompting from authorities and its own consultants, the operators moved
quickly to remedy those defects.
The ERD Committee's major finding as to the "probable cause of the
leakage" was -
- long term leakage from the unlined minewater evaporation pond;
- long term leakage from the unlined washwater evaporation pond, exacerbated
by the presence of dolines in the pond;
- sustained ponding of supernatant liquor over sections of the tailings
storage cells;
- direct contact between the tailings liquor and the floor of the tailings
storage cells, particularly in the period immediately after the breaching
of a temporary bund in Cells 2 and 3 when liquor flowed onto the bare
surface of the cells.
In commenting on the possible effect of the leakage, the ERD Committee
found " that, on the basis of current evidence, there have been no
harmful effects to employees, the local community or the environment arising
out of the leakage from the tailings retention system at Olympic Dam and
that it is highly unlikely that any such harmful effects will emerge in
the future."
The major caveat upon such findings was "the lack of knowledge about
what has actually happened to the leaked liquor under Olympic Dam. More
scientific studies are obviously necessary."(p 7)
In another finding the ERD Committee reported that "the changes
to the tailings retention system undertaken by the Olympic Dam operators
in response to the leakage have been undertaken with commendable zeal
and that they appear to represent an appropriate response to the leakage
which will minimize the likelihood of future problems provided the new
system is properly constructed, monitored and managed."
A second major concern about the Olympic Dam Operation is its use of
water from the Great Artesian Basin. Until 1996 all water was drawn from
Wellfield A, developed between 1983 and 1992. Wellfield A, located 100
kilometres north of the mine in the Great Artesian Basin, met water requirements
of approximately 15 megalitres per day. With the opening of Wellfield
B, water abstraction from Wellfield A has been reduced to 6-9 megalitres
a day.
Wellfield B, located further into the Great Artesian Basin, became operational
in September 1996. Approved abstraction rate is 42 megalitres per day.
The Olympic Dam Operation uses approximately three per cent of water
drawn from the South Australian section of the Great Artesian Basin. The
following table provides information on use of water from the South Australian
section:
Groundwater discharge in the South Australian portion of the Great
Artesian Basin
Outflow |
Share of total
discharge
|
ML/d |
% |
Pastoral bores
Flowing bores a
|
130 |
29 |
Springs
Dalhousie
Others
|
54
12
|
12
3
|
Olympic Dam/Roxby Downs |
15 |
3 |
Gas/Petroleum |
22 |
5 |
Vertical leakages b |
217 |
48 |
Total |
450 |
100 |
a Includes towns and homesteads, except Roxby Downs and Moomba.
b Difference between discharge and estimated recharge for the
South Australian portion of the Great Artesian Basin.
Source: Mines and Energy South Australia (personal communication,
December 1995).
Reprinted from: Lake Eyre Basin - an economic and resource profile
of the South Australian portion, ABARE Research Report 96.1, 1996, 48
The South Australian Government has informed the Committee that observed
drawdowns in water pressure and decline in spring flows are generally
less than originally predicted and within the accepted level of impact.
"As was predicted in the EIS [environmental impact statement] (1982),
two springs have ceased to flow. However, in some areas the rate of drawdown
was greater than expected and approached the limits imposed by the Special
Water Licence. In addition the reduction in flows at some springs (notably
Bopeechee) was greater than anticipated. These effects were found to be
due in part to geological structures not identified at the time the initial
modelling took place." (S 109, 9)
Great Artesian Basin, South Asutralian Section - Mound
Springs
The South Australian Government report:
The water abstraction regime has been modified to minimise these
effects. In addition reinjection of water is being undertaken to raise
the piezometric head in order to reverse the decline in Bopeechee Springs,
and the development of Borefield B was accelerated in order to reduce
the overall abstraction rate from Borefield A. (S 109, 9)
The South Australian Government has stressed that these impacts were
detected by the monitoring program and that appropriate remedial action
was initiated to prevent any long term effects on the Great Artesian Basin
and particularly the local mound springs beyond those predicted in the
environmental impact statement. In addition, WMC have implemented an extensive
water conservation policy which is aimed at minimising the amount of water
extracted from the Great Artesian Basin (S 109, 9-10).
According to the Australian Conservation Foundation, " [t]he excessive
quantities of water required by the mine and the positioning of borefields
is resulting in long-term degradation of mound springs as well as serious
depletion of groundwater tables" (S 81, 1.1.2, 5).
The Conservation Council of South Australia/Friends of the Earth Nouveau
submission expressed a similar fear that because the springs are shallow
and often small in area they will without an adequate flow of ground water
rapidly dry up and be irreparably damaged (S 92, 12).
The Committee's conclusion is that concerns about the water being drawn
from the Great Artesian Basin are insufficiently focussed to lead to any
firm recommendation other than that the monitoring program referred to
by the South Australian Government should be maintained.
The Conservation Council of South Australia/Friends of the Earth Nouveau
stated that because pastoralists in the area are now being charged for
water drawn from the Great Artesian Basin, there should also be a charge
for water drawn for use in the Olympic Dam Operation. (S 92, 19). Enquiries
disclosed that no such charges are being levied.
A second justification for a charge on water from the Great Artesian
Basin lies in cost recovery user pay principles under the National Competition
Policy. A purpose of this policy is to build in an economic incentive
to minimise water usage and consequent environmental impact (S 92, 19).
The Committee does not agree. The water does not come to WMC without
cost. The plant needed to collect the water and pipe it to the mine site
costs in excess of $100 million. Although the water is also used in Roxby
Downs, no other body makes any contribution to the costs. On the basis
of evidence presented to it on this occasion the case for departing from
the policy of non-discrimination in charging for water from the Great
Artesian Basin has not been made.
For areas where charges are levied for water, for example for reticulated
water in metropolitan and more closely settled rural areas, the principal
purpose of those charges is to meet the capital and recurrent costs of
the reticulation system.
As already recorded, WMC has invested $100 million in infrastructure
to draw water from the Great Artesian Basin. In other words, it is meeting
the full cost of drawing its water supply and of monitoring the impact
of its water usage to preserve the viability of the Basin and its environmentally
sensitive aspects.
Included in the infrastructure are facilities for continuous long-term
modelling providing the capacity to reforecast the impact of pumping and
adjust it as required to avoid any detrimental impact.
REHABILITATION OF FORMER MINES
From the first phase of uranium mining in Australia there are several
abandoned mines: Radium Hill; Rum Jungle; various mines in the South Alligator
Valley; and Mary Kathleen. Rehabilitation of these mines was never properly
planned during the life of the mine, nor was finance organised as part
of the business.
Nabarlek, the first mine of the second phase, is now in the process of
rehabilitation. Rehabilitation was planned even before mining commenced.
It represents a very different approach to mining.
The purpose of this part of the chapter is to review rehabilitation practices
and activity.
Radium Hill
The South Australian Government has stated that "only minimal rehabilitation
of the wastes was undertaken" when the mine at Radium Hill was closed.
Tailings from the upgrading process undertaken at the site remained as
a "pile". "Although this material consisted mainly of mineralised
sands and mica, with a low radionuclide content, it was unprotected from
wind and water erosion." (S 109, 14)
In the last decade, Radium Hill wastes have been covered with approximately
3 metres of soil and revegetated. Other wastes such as drill cores were
collected and buried in the tailings pile.
When the mine was in operation, uranium concentrate was taken by railway
to a treatment plant at Port Pirie where the uranium was extracted. The
tailings containing the bulk of the residual radioactivity in the ore
remained in clay lined dams at Port Pirie. These dams are on a tidal swamp
and were threatened with inundation during extreme tides. The tailings
were uncovered with no control over dust raising or radon emission.
These tailings have been covered with about 2 metres of slag (from the
adjacent smelter) and topsoil, and have been revegetated. The site generally
has been protected from high tides by extensive mounds of slag.
An independent consultant recently inspected both sites and considered
them, subject to minor repairs, to be in good condition. (The above account
is based on the South Australian Government submission, 109, 14-5; see
also S 92, 10).
The Committee is not convinced, on the evidence before it, that rehabilitation
and remedial work has been satisfactorily completed. It recommends a full
public evaluation of the work as soon as possible and that the sites be
reappraised at intervals of not more than two years.
South Alligator
Between 1954 and 1964 there were 13 uranium mines in the upper reaches
of the South Alligator River. These mines are spread in a belt about 2
km wide and 20 km long from Coronation Hill in the southeast to near UDP
Falls ("Gunlom") in the northwest. (Another mine at Sleisbeck
in the headwaters of the Katherine River was worked in 1957. Ore from
this mine was processed at Rum Jungle.)
Most of the ore from these mines was processed at Moline, although some
was processed in a small mill built on the El Sherana-Gunlom road.
There was little clean-up when operations ceased.
The tailings dumps at Rockhole and Moline were poorly constructed and
over time radioactive tailings escaped into the drainage system.
At Moline, tailings had travelled more than 10 km downstream of the breached
containment structure. The containment was poorly confined and failed
after only one wet season following abandonment of the mine in 1972.
At Rockhole, water carrying radioactive tailings had flowed into the
adjacent South Alligator River.
In 1992 the Supervising Scientist, in consultation with the Australian
Nature Conservation Authority and the Department of Primary Industries
and Energy, supervised a program of hazard reduction works in the valley.
These works consisted of collapsing or barring entrances to adits; fencing
around pits; and burying contaminated wastes of all types at newly constructed
containment sites.
Tailings from the Rockhole area were removed and reprocessed at Moline
to extract gold and then placed in the tailings containment structure
at Moline.
After scraping, the Rockhole tailings area was ripped and revegetated.
No new soil was imported into the area.
Gamma dose rate surveys were carried out when work was completed to ensure
that radiation levels had been brought below the required levels.
The public dose rate from radiation was reduced to below the public limit,
thus enabling the area to be managed as a national park without the need
for serious restrictions on visitor access.
(Paraphrase from Supervising Scientist submission, 85, 6-7).
Moline
Moline was the location for tailings derived by processing ore from a
series of base metal operations nearby and uranium/gold ore from the South
Alligator area.
The tailings were inadequately deposited and about 25 per cent were carried
away, eventually to the Mary River flood plain.
The Supervising Scientist states: "No evidence of permanent environmental
impact arising from the tailings has been noted. This may partly be due
to the total drying of the creek system each dry season, and the difficulty
in determining impacts in such a naturally variable ecosystem." (S
85, 7)
According to the Supervising Scientist: "The tailings repository
radiation protection was capped by contractors [Pacific Territory Department
of Mines and Energy in 1991-92 and covered with a rock mulch as erosion
protection. A radiation survey was undertaken at the under the supervision
of the end of rehabilitation work to ensure Gold Mines] Northern that
targets had been met." (S 85, 7)
The cost of rehabilitation was recovered by the company through retreatment
of tailings for gold.
(Based on Supervising Scientist submission, 85, 7; and Northern Territory
Government submission, 100, 7).
Mary Kathleen
This mine was rehabilitated by the company, in which Rio Tinto Mining
Co of Australia Ltd had a majority of shares, according to the code of
practice on the mining and milling of radioactive waste.
According to Canning Resources, a subsidiary of Conzinc Riotinto, rehabilitation
was provided for in a full environmental impact study undertaken before
the mine reopened in 1976. Canning Resources state: "Mary Kathleen
then became the site of Australia's first major rehabilitation project
of a uranium mine, which was completed at the end of 1985 at a cost of
some $19.5 million. In 1986 this work won an award from the Institution
of Engineers Australia for environmental excellence." (S 65, 12)
The Australian Conservation Foundation commented: "There is a view
that at the time of the mine's closure the rehabilitation would not have
met with the standards of the OSS. The tailings dam was clearly leaking
and it would be a matter of good luck rather than good management that
there would not be adverse environmental impacts arising from the leakage"
(S 81, 1.3, 7).
Westmoreland Area, Northern Territory
Ore from five small mines in this area near the Queensland border was
trucked more than 1800 km to Rum Jungle for processing.
According to the Supervising Scientist, "[e]nvironmental impacts
were small as the workings were mainly small shafts and shallow open cuts
. . . radiation from old stockpiles was potentially hazardous." (S
85, 9)
Remedial and hazard reduction works have been undertaken according to
a plan drawn up by DPIE in 1988, work being completed as funds have become
available. The Supervising Scientist has commented: "Completed sites
have achieved levels of gamma radiation low enough to permit public access
for lengthy periods, but not permanent occupancy."
(S 85, 9)
Rum Jungle
In two decades of mining and milling, of copper as well as uranium, some
600,000 tonnes of tailings were produced and spread over about 31 ha.
Supernatant liquid, which also contained some suspended tailings, drained
over a spillway and thence flowed into the Finniss River. Research on
the Finniss River has shown that the main agent causing the damage was
copper. There was also some wind dispersal of tailings.
Containment of pollutants was not part of an initial clean-up organised
in 1977.
In a joint Commonwealth/Northern Territory Government hazard remediation
program completed in 1986, tailings and contaminated soil were placed
in the Dyson's Open Cut. The Supervising Scientist has observed, citing
Verhoeven:
No special preparation of the pit was undertaken prior to placement of
the tailings. The pit was then sealed with waste rock and a final soil
cover and vegetated. The tailings dam site was covered with topsoil, surface
drainage was installed and the whole area revegetated. (S 85, 7-8)
Owing to the sulphides in the ore bodies, these measures were unsuccessful
and were the main cause of the severe environmental impact to the aquatic
ecosystem of the Finniss River for 10 or more kilometres downstream. It
is considered that environmental problems derived from the copper rather
than uranium.
Another rehabilitation program was considered "generally successful,
and life has returned to the Finniss River." (S 85, 8)
The "sustainability of the site is still not certain" (S 85,
9).
The copper mine at Rum Jungle Creek South has also been the subject of
a remedial action program, as have other small mines in the district.
Rum Jungle - Abandoned and neglected until recently
Nabarlek
Nabarlek is the first mine to be opened in which rehabilitation was part
of the original planning. A benefit of addressing rehabilitation as part
of the planning and operation of the mine is a substantial reduction in
cost. According to Queensland Mines, the owner, "the cost of the
work has been less than one quarter of rehabilitation projects costs (per
unit uranium produced) at other uranium mines in recent times." (S
78, 3)
According to Queensland Mines, techniques in rehabilitation included
in-pit tailings disposal, tailings preconsolidation, holistic rehabilitation
planning, revegetation, use of Caro's Acid, induction and training, environmental
monitoring programmes, water management and radiation safety. (S 78, 8)
The total cost of decommissioning was about $8 million.
Nabarlek was the subject of examination by the Supervising Scientist
throughout the life of the mine. There was one "major" incident
during a cyclonic storm in March 1981. "Because of the origin of
the runoff water and the dilution from the storm, it was considered that
no environmental degradation resulted." (S 85, Attachment C)
The Supervising Scientist has described other incidents as "all
minor and of little consequence." In all, fifteen incidents or unusual
occurrences are recorded in the annual reports of the Supervising Scientist"
(see Appendix 2.10 for a list) (S 85, Attachment C).
The Supervising Scientist has also noted:
Other matters causing effects on the environment include the
tree death in the Forest Irrigation Area. Leaching from this area has
left a chemical signature in a small creek downstream. Investigations
by ERISS are continuing so as to determine if there was any effect on
the fish in this creek.
The introduction of some weeds can also be ascribed to the establishment
of the mine. Weed species include Mission grass Penisetum polystachion;
Grader grass, Themeda quadrivalvis and Hyptis, Hyptis suavalens.
The company has pursued an active weed monitoring and control program
which is continuing into the post rehabilitation period. (S 85, Attachment
C)
The Supervising Scientist's appraisal is as follows:
The standard of the rehabilitation works is world class and a
good example of what modern mine environmental engineering can achieve.
The tailings were deposited in the pit during operations. All radioactively
contaminated material was placed above the tailings in the pit and then
covered with waste rock. All structures have been removed or demolished
(other than those transferred to the traditional owners, which are in
the process of being dismantled and/or relocated). The disturbed ground
was been prepared, seeded with local tree species and fertilised in
late 1995 and significant grass and tree growth is already evident.
Assessment of the adequacy of rehabilitation and revegetation is to
be made by an independent expert chosen jointly by the mining company,
the Northern Land Council, and government authorities. (S 85, Attachment
C, Summary)
The Northern Land Council have appraised Nabarlek rehabilitation in the
following terms:
The goals of rehabilitation were formulated in consultation with
the Aboriginal landowners, and the rehabilitation design was scrutinised
by the NLC. Aboriginal landowners of the minesite made several inspections
of developments during the decommissioning process, and continue to
do so.
The physical structure of the Nabarlek Uranium Mine has largely
disappeared. Replacing the pit, plant, stockpiles and evaporation ponds
is a low relief area with a surface of waste rock and soil. Grasses,
young shrubs and tree seedlings are already covering much of this surface,
however the success of the rehabilitation has yet to be determined.
QMPL will be released of their responsibility for maintenance of the
site when the NLC and Aboriginal landowners are satisfied that they
will be left with a landscape that blends into the surrounding environment,
and will not be a liability to them or their descendants.
Nabarlek has continually been subject to less scrutiny than the
Ranger Uranium Mine by government, environmental groups and the general
public because it lies within Arnhem Land and is less accessible. The
fact that environmental management of the mine has been to such a high
standard is due in part to the corporate policy of QMPL, but largely
due to the fact that high standards of environmental management and
adherence to environmental requirements were contractually enforced
by the NLC. (S 42, 7)
The Committee had to reply on evaluations by the Supervising Scientist.
Unfortunately the Australian Conservation Foundation, for example, commented
only briefly on rehabilitation at Nabarlek, merely noting that the Northern
Territory Government has yet to cancel the financial arrangement to cover
the costs of rehabilitation because "a benchmark for successful rehabilitation
has never been set" (S 81, 7, citing Dennis Schulz, The Bulletin,
February 1996).
Subsequently, in evidence, Mr Michael Krockenberger, Campaigns Director,
ACF, told the Committee: "I do not think . . . you can draw any conclusions
from Nabarlek yet; Nabarlek has not even been completed in terms of its
rehabilitation (23 August 1996, 318).
Narbarlek - Planned and monitored