Chapter 1
Background
Introduction
1.1
On 25 September 2014, on the recommendation of the Senate Selection of
Bills Committee, the Senate referred the National Water Commission (Abolition)
Bill 2014 (the bill) to the Senate Environment and Communications Legislation
Committee (the committee) for inquiry and report by 24 November 2014.[1]
1.2
The reasons for referral were that the National Water Commission (NWC):
-
is the only independent federal body that tracks water policy;
-
advises Council of Australian Governments (COAG) and the
Australian Government on water policy;
-
audits the effectiveness of the implementation of the
Murray-Darling Basin Plan;
-
promotes water reform; and
-
that many organisations have expressed concern at its proposed
axing.
1.3
The principal issues for the committee's consideration were the impact
of the bill on the continuation of robust, independent and transparent
monitoring and assessment of matters of national water reform and on the
management of Australia's water resources.[2]
Conduct of the inquiry
1.4
In accordance with its usual practice, the committee advertised the
inquiry on its website and wrote to relevant individuals, organisations and
state government ministers inviting submissions by 13 October 2014.
1.5
The committee received 32 submissions, which are listed at Appendix 1.
The submissions may be accessed through the committee's website at:
https://www.aph.gov.au/Parliamentary_Business/Committees/Senate/Environment_and_Communications/NWC
1.6
The committee held a public hearing in Canberra on 4 November 2014. A
list of witnesses who appeared at the hearing may be found at Appendix 2.
1.7
The committee thanks all the organisations and individuals that made
submissions to the inquiry and all the witnesses who participated in the public
hearing.
Note on references
1.8
Hansard references in this report are to the proof committee Hansard.
Page numbers may vary between the proof and the official Hansard transcript.
Background to the bill
1.9
The following discussion provides a brief overview of the implementation
of the National Water Initiative (NWI) and the establishment of the National
Water Commission (NWC).
Intergovernmental Agreement on a
National Water Initiative
1.10
In June 2004, all members of COAG, except Western Australia and Tasmania,
reached agreement to implement a National Water Initiative
(NWI).[3]
Tasmania subsequently became a party to the agreement in June 2005, as did
Western Australia in April 2006.[4]
1.11
The NWI was intended to continue reforms that had been initiated by the
1994 COAG Water Reform Framework, under which most jurisdictions had undertaken
significant reforms to their water management systems, including:
...separating water access entitlements from land titles,
separating the functions of water delivery from that of regulation, and making
explicit provision for environmental water.[5]
1.12
It was intended that the full implementation of the NWI would result in:
...a nationally-compatible, market, regulatory and planning
based system of managing surface and groundwater resources for rural and urban
use that optimises economic, social and environmental outcomes...[6]
1.13
These overarching objectives were to be delivered by implementing the
following specific reforms:
- clear and nationally-compatible
characteristics for secure water access entitlements;
-
transparent, statutory-based water
planning;
-
statutory provision for
environmental and other public benefit outcomes, and improved environmental
management practices;
-
complete the return of all
currently overallocated or overused systems to environmentally-sustainable
levels of extraction;
- pogressive removal of barriers to
trade in water and meeting other requirements to facilitate the broadening and
deepening of the water market, with an open trading market to be in place;
-
clarity around the assignment of
risk arising from future changes in the availability of water for the
consumptive pool;
-
water accounting which is able to
meet the information needs of different water systems in respect to planning,
monitoring, trading, environmental management and on-farm management;
-
policy settings which facilitate
water use efficiency and innovation in urban and rural areas;
-
addressing future adjustment
issues that may impact on water users and communities; and
-
recognition of the connectivity
between surface and groundwater resources and connected systems managed as a
single resource.[7]
1.14
Schedule A of the NWI sets out a timeline for the implementation of
specific actions to be taken by the parties to the agreement, most of which
were to be completed by 2012.[8]
Establishment and role of the
National Water Commission
1.15
The first action to be completed under the implementation timetable of
the NWI was the establishment of the NWC by the end of 2004.
1.16
The NWI further specified that the commission be established and funded
by the Commonwealth and have up to seven members, including a chair, with
expertise in audit and evaluation, governance, resource economics, water
resources management, freshwater ecology and hydrology. Four of the members,
including the chair, were to be appointed by the Commonwealth and three by the
states and territories.[9]
1.17
The NWI also specified that the roles of the commission include 'to
assist with the effective implementation' of the NWI, to accredit the progress
of parties against the implementation timetable and to provide advice to COAG
on national water issues.[10]
1.18
The NWC was subsequently established by the National Water Commission
Act 2004 (NWC Act), which commenced on 17 December 2004.
1.19
The NWC work program consists of a number of reporting and auditing
mechanisms, including the statutory function of assessing progress towards the
implementation of the NWI.[11]
In addition, the NWC has acquired the role of auditing the effectiveness of the
implementation of the Basin Plan.
Assessments of the NWI
1.20
Since its inception, the NWC has undertaken biennial assessments of
progress made towards NWI objectives in 2007, 2009 and 2011. A final assessment
was delivered in 2014, after amendments to the NWC Act in 2012 moved the
reporting timetable to a triennial basis.
Functions in relation to the
Murray-Darling Basin Plan
1.21
With the introduction of the Water Act 2007, the NWC
acquired a new function to conduct audits of the effectiveness of the
implementation of the Murray-Darling Basin Plan (Basin Plan) and associated
water resource plans.
1.22
The NWC published its first report on the Basin Plan in March 2013. As
the plan only commenced in November 2012, this report does not constitute a
full audit as there had been insufficient activity or reporting in the
intervening period.[12]
1.23
The NWC concluded that, although a vast effort had gone into the
preparation of the Basin Plan itself over the preceding five years,
implementation planning remained at an early stage. In the NWC's opinion, 'the
next two years will be critical in establishing momentum and direction for
Basin Plan implementation'.[13]
COAG review of the National Water
Commission
1.24
The NWC Act originally included both a mandatory review provision and a
sunset provision. Section 38 of the original NWC Act specified that a review
must be conducted into the ongoing role and functions of the NWC by the end of
2011 and section 39 specified that the NWC Act would cease to be in force on 30
June 2012.[14]
1.25
The mandatory review called for by section 38 was completed by Dr David
Rosalky in December 2011. The review found that, while some essential elements
of the NWI had been implemented, the timetable for the completion of the NWI's
milestones had proved to be ambitious as several key initiatives had, at that
time, not been implemented due to technical and political constraints.[15]
1.26
The review further found that the NWC, or a body very similar to it,
would play an important role in achieving those parts of the NWI that remained
outstanding:
The elements of the NWI still to be implemented are, by their
nature, the more difficult ones and the role that can be played by a specialist
and independent body like the NWC is likely to be even more important in the
future.[16]
1.27
The review identified three key activities that would be required to
implement further reforms—monitoring and audit of reform activity, assessments
of reform activity and knowledge leadership—and argued that having a dedicated and
independent entity responsible for all three activities 'enhances the
efficiency and effectiveness of each of the individual activities'.[17]
1.28
The review concluded that 'the NWC should continue, without sunset, for
the duration of the NWI agenda and within essentially the same governance
arrangements that it now has with its legislation strengthening its
independence as a COAG body'.[18]
National Water Commission Amendment
Act 2012
1.29
The Commonwealth Government's response to the review was given
legislative effect by the National Water Commission Amendment Act 2012 which
removed the sunset clause thereby allowing the NWC to continue to operate for
the duration of the NWI. In addition, the functions of the NWC were reframed to
focus on three main areas—monitoring, audit and assessment, the number of
commissioners were reduced from seven to five, and the commission's performance
was made subject to review once every five years.[19]
Proposed abolition of the NWC
1.30
The terms of reference for the National Commission of Audit, established
after the 2013 federal election, included suggesting options for the
consolidation of agencies and boards.[20]
In phase one of its report, delivered in February 2014, the Commission of Audit
suggested that the NWC could be either consolidated into the Department of the
Environment with the intention of saving on administrative costs, or abolished,
with its monitoring, audit and assessment functions transferred to the
Productivity Commission.[21]
1.31
The latter suggestion was adopted by the Government, which announced in
the 2014–15 Budget that it would achieve savings of $20.9 million over four
years by closing the NWC in December 2014 and transferring its statutory
functions to other government bodies. These projected savings take into account
the cost to other agencies of taking on NWC functions.[22]
1.32
The National Water Commission (Abolition) Bill 2014 would give effect to
this plan. The bill would repeal the NWC Act and, by amending the Water Act
2007, transfer the two statutory NWC functions to the Productivity
Commission—triennial assessments of progress on implementation of the NWI and five-yearly
audits of the implementation of the Basin Plan and associated water resource
plans.[23]
1.33
The Productivity Commission will be required to provide its reports on
the implementation of the Basin Plan to the Murray-Darling Basin Authority
(MDBA) and each of the basin states. It will also be required to provide its
reports on the implementation of the NWI to COAG.[24]
1.34
At its budget estimates hearings on 26 May 2014, the committee was
informed that several functions currently undertaken by the NWC would cease
with its abolition. These functions include:
-
preparation, at the request of COAG, of a national water planning
report card, which provides a summary of water planning across Australia and
the level of progress that has been achieved in each planning area;
-
preparation of a national performance report on urban water
utilities, in accordance with clauses 75 and 76 of the NWI, which provides an
annual, independent and public report by which to compare pricing and service
quality; and
-
assistance with the effective implementation of the NWI, which
includes facilitating interaction between the states and providing 'thought
leadership' on water reform.[25]
1.35
The committee was informed at its supplementary estimates hearing on
20 October 2014 that the Bureau of Meteorology had undertaken to continue
the non-statutory function of reviewing the performance of urban water
utilities for the next 12 months. A similar report on rural water
utilities currently undertaken by the NWC will not be continuing.[26]
Overview of bill provisions
1.36
The bill gives effect to the Government's announcement in the 2014–15
Budget of its intention to abolish the NWC by the end of 2014 while
transferring key functions to existing Commonwealth agencies.[27]
1.37
The two statutory functions of the NWC that are maintained by the bill
are triennial assessments of progress on implementation of the NWI and audits
of the implementation of the Basin Plan and associated water resource plans.
The bill proposes to transfer these two functions to the Productivity
Commission.
1.38
To carry out these changes, the bill proposes to repeal the National
Water Commission Act 2004 and amend the Water Act 2007.
Repeal of the National Water
Commission Act 2004
1.39
Item 1 of the bill proposes to repeal, in its entirety, the National
Water Commission Act 2004.
Amendments to the Water Act 2007
1.40
The remaining items of the bill propose amendments to the Water Act
2007.
1.41
Items 2 to 4 insert new definitions into the Water Act.
1.42
Item 5 proposes to repeal subsection 74A(4) of the Water Act, which
provides that the minister may seek advice from the NWC when making or revoking
a determination that a basin state has applied the NWI risk assignment
framework under state legislation.
1.43
Item 6 repeals part 3 of the Water Act, which currently provides the NWC
with the power to conduct audits of the implementation of the Basin Plan,
details when such audits must be completed and states to whom the audit reports
must be provided.
1.44
Item 6 also substitutes a new part 3 which will require the Minister to
refer to the Productivity Commission both the audit of the implementation of
the Basin Plan and associated water resource plans, and the triennial
assessments of progress on implementation of the NWI. This new part 3 also includes
provisions for when these activities must be undertaken and to whom the
resulting reports must be provided.
1.45
Items 7 to 11 contain transitional provisions, including the transfer of
NWC records to the Department of the Environment, the transfer of Ombudsman
investigations to the Department and the tabling of the NWC's final annual
report.
Navigation: Previous Page | Contents | Next Page