Chapter 1

Chapter 1

Introduction

Referral to the Committee

1.1        On 16 June 2008, the Senate referred the Renewable Energy (Electricity) Amendment (Feed-in-Tariff) Bill 2008 (hereafter 'the bill') to the Senate Environment, Communications and the Arts Committee for inquiry and report by 14 October 2008. On 25 September 2008 the Senate granted an extension of time to report until 10 November 2008.

1.2        The committee advertised the inquiry in the Australian newspaper. Details of the inquiry were placed on the committee's website and the committee also wrote to a number of organisations and stakeholder groups inviting written submissions by 15 August 2008.

1.3        The committee received submissions from 129 individuals and organisations, as listed at Appendix 1. The committee also held public hearings in Sydney on Monday 8 September, in Melbourne on Tuesday 9 September and in Canberra on Thursday, 16 October 2008. A list of those who gave evidence at this hearing is at Appendix 2. The broad majority of submissions were supportive of feed-in tariffs, as discussed in chapter 3. The committee thanks all those who assisted with its inquiry.

 

What is a Feed-in Tariff?

1.4        Most electricity is generated by a small number of large power stations. Their energy is distributed, through the electricity grid, to many consumers. However, it is possible for electricity to be produced by small dispersed generating units, which are often based on renewable energy technologies such as wind or photovoltaic cells.

1.5        A feed-in tariff (FIT) is a policy mechanism used to encourage the use of both small dispersed generating capacity and large 'utility-scale' generators. A FIT is a rate, usually set by a regulator or government, which electricity retailers or a regulator are required to pay to particular electricity generators who want to feed power into the electricity grid. A FIT will:

put a legal obligation on utility companies to buy electricity from renewable energy producers at a premium rate, usually over a guaranteed period, making the installation of renewable energy systems a worthwhile and secure investment for the producer. The extra cost is shared among all energy users, thereby reducing it to a barely noticeable level.[1]

1.6        There are at least two main reasons why a FIT may be set.[2] It may be intended to correct a market failure, such as a lack of a price signal reflecting the environmental harm caused by greenhouse gas emissions. It may also be used to stimulate the development of particular electricity generating technologies, such as photovoltaic cells. Often these two reasons are closely related, and the objectives of a FIT are discussed further in chapter 2.

 

The bill

1.7        The bill seeks to amend the Renewable Energy (Electricity) Act 2000 (hereafter 'the Act') to establish a national FIT law. The object of the bill is to support the greater commercialisation of renewable energy technologies by:

(a) providing specifically tailored support for a range of renewable energy technologies that are currently not adequately assisted by the mandatory renewable energy target;

(b) requiring electricity retailers to permit owners of qualifying generators to supply the electricity grid with electricity generated from selected renewable energy sources;

(c) providing a payment to owners of qualifying generators for the renewable electricity which they produce from renewable energy sources installed after the commencement of this Act;

(d) establishing an effective monitoring regime to monitor the extent of production of renewable electricity by owners of qualifying generators.[3]

 

Issues to be considered

1.8        FITs are complex policy instruments that are challenging to successfully design and implement.[4] The many issues that must be carefully addressed include:

1.9        In addition, any national approach to FITs must address the range of existing state and territory FIT schemes. Any FIT scheme must also be tailored to interact effectively with other climate change and energy policy instruments, such as an emissions trading scheme and renewable energy targets.

 

Existing FITs

1.10      There are FIT schemes already operating in some Australian states and territories. The committee notes that FIT policies are under discussion by the Council of Australian Governments (COAG).  At its meeting of March 2008, COAG agreed 'to consider options for a harmonised approach to renewable energy feed in tariffs in October 2008'.[5] The committee understands this consideration is ongoing.

1.11      Currently, there is some form of FIT in the Australian Capital Territory, Queensland, South Australia and Victoria. A FIT has also been piloted in the Alice Springs Solar Cities program. The schemes vary significantly in their design.[6] Some of these FIT schemes are restricted to new installations, others are not. Some offer a FIT for all electricity generated, others for only the electricity that is surplus to the users' needs. Some have set limits for the scheme (such as a target number of megawatts of electricity generation), others have not. These differences in FIT schemes mean there is no consistent national approach. All these design choices raise significant policy questions, discussed in the next two chapters.

1.12      In addition, the existing Australian state and territory schemes have various eligibility restrictions. In Victoria, the scheme is limited to installed units of up to two kilowatt hours (kWh) generating capacity, and the scheme as a whole is capped at 100 megawatts (MW) of generating capacity.[7]

1.13      South Australia also limits the size of customers and systems eligible to participate. Its eligibility criteria are that the system must:

1.14      Queensland has a scheme similar to that in South Australia. The conditions of eligibility in Queensland are that customers must:

1.15      Customers must also meet the costs of installation of new electricity meters. The Queensland scheme is subject to review once a level of 8MW of capacity is installed state-wide.[10]

1.16      The Australian Capital Territory's scheme in contrast has very few eligibility limits. While large generators receive a less generous feed-in tariff than household-sized installations, there is no size limit on individual generators (unlike Queensland, Victoria and South Australia) and no upper limit on the number of participants or number of MW that can be eligible for the feed-in tariff (in contrast to limits or reviews in Victoria and Queensland).[11]

1.17      The table below summarises some key features of current Australian FIT schemes.

Location

Size limits to individual installations

Limits or caps to scheme

Net or gross

New or existing

Value of FIT

Eligible sources

South Australia[12]

<10kVA single phase / <30kVA three phase

Review at 2.5 years or when 10MW installed

Net

Both

44 c / kWh (minimum)

PV only

Victoria[13]

2kW

Limit of 100MW

Net

Both

60 c / kWh (approx 4 times retail)

PV only

Queensland[14]

<10kVA single phase / <30kVA three phase

Review at 8MW installed

Net

Both

44 c / kWh

PV only

ACT[15]

None, but tariff reduces for large installations

None

Gross

Both

3.88 * retail tariff

Solar and wind

Alice Springs Solar Cities[16]

Not known

Limit of 225 installations

Gross

New only

45 c / kWh

PV only

Policy issues that arise in the design of a FIT scheme are discussed in the following chapters.

Navigation: Previous Page | Contents | Next Page