Appendix 3
Table 1: DBCDE Summary of Six Stage Generic Development Pipeline for
Greenfield Development and Major Brownfield Redevelopment
Stage
|
What happens
|
Time for stage
|
Time elapsed since start
|
Time to premises construction
|
1. Identification and designation of new land release areas
|
Inclusion in urban zoning or master planning. Initiated by local or
state government or private proponent.
|
2–4 years
|
2–4 years
|
6.25–15 years
|
2.
Gazettal of rezoning or change of land use
|
Rezoning under local planning
instruments. Initiated by proponent.
|
1–3
years
|
3–7
years
|
4.25–11
years
|
3. Negotiation of infrastructure levies and detailed structure
planning
|
More detailed site planning, possibly determination of developer
contributions. Done by developer. Involves many agencies e.g. roads, water,
electricity, sewer and public transport; also schools etc.
|
1–3 years
|
4–10 years
|
3.25–8 years
|
4. Statutory subdivision and development approval
|
Approval of developer-initiated applications on a stage by stage
basis – road layouts, sometimes integrated housing projects.
|
0.5–2 years
|
4.5–12 years
|
2.25–5 years
|
5. Major civil works, servicing of allotments, and issue of new
titles
|
Engineering designs, building, and certification of civil works.
Construction done by the developer, certification by state utilities.
|
1–2 years
|
5.5–14 years
|
1.75–3 years
|
6. Development approvals and dwelling construction
|
Housing design, approval and construction including placement of
house on block.
|
9–12 months
|
6.25–15 years
|
0.75–1 year
|