Department of Defence — Submarine Rotational Force—West, Priority Works, HMAS Stirling, Western Australia and other works

REPORT - August 2024

List of recommendations

2.48The Committee recommends that the House of Representatives resolve, pursuant to section 18(7) of the Public Works Committee Act 1969, that it is expedient to carry out the following proposed works: Department of Defence – Submarine Rotational Force – West, Priority Works, HMAS Stirling, Western Australia.

3.42The Committee recommends that the Department of Finance consult with the Australian Federal Police regarding the security aspects of the fit-out design:

Immediately, for the proposed works, and

At a much earlier stage for any CPO fit-out works in the future.

3.43The Committee recommends that the House of Representatives resolve, pursuant to section 18(7) of the Public Works Committee Act 1969, that it is expedient to carry out the following proposed works: Department of Finance -Proposed Fit-out of New Commonwealth Parliament Offices at One Festival Tower, Adelaide, South Australia.

4.34The Committee recommends that the House of Representatives resolve, pursuant to section 18(7) of the Public Works Committee Act 1969, that it is expedient to carry out the following proposed works: Reserve Bank of Australia – Head Office Storage and Logistics Change.