Chapter 2 The Proposed Works
Purpose
2.1
According to DFAT, the purpose of the proposed work is to extend and
refurbish the existing Chancery in Beijing to meet increased office
requirements of both DFAT as well as attached agencies that include the
Australian Trade Commission (Austrade), the Australian Agency for International
Development (AusAID), the Australian Centre for International Agricultural
Research (ACIAR), the Australian Customs Service (ACS), the Australian Federal
Police (AFP), the Department of Agriculture Fisheries and Forestry (DAFF), the
Department of Defence, the Department of Education, Science and Training
(DEST), the Department of Immigration and Multicultural Affairs (DIMA),
Department of the Treasury, and Invest Australia.[1]
Need
2.2
DFAT submitted that pressure on office space has been in evidence since
the existing Chancery building was completed in 1992, exacerbated by the need
to meet the demands of attached agencies, beginning with the conversion of two
staff apartments to offices to accommodate AusAID staff, and the conversion of
the Chancery auditorium to office space.[2]
2.3
In 1997 a prefabricated temporary annex of 300 square metres was built
to meet rapidly growing accommodation needs. The annex as well as the chancery
is now crowded, placing pressures on the building and building services
(including heating and ventilation) as well as increasing security pressures.
Further, the current layout has evolved in an ad hoc way and does not
meet efficient work practices.[3]
2.4
The annex is linked to the main chancery building at one level only by a
narrow circular staircase that does not meet Building Council of Australia
(BCA) standards or disability access requirements. Lighting and acoustics are
also sub-standard.[4]
2.5
A consultants report commissioned by DFAT in May 2003 identified a net
shortfall of 1,085 square metres of office space, poor efficiency of space
usage, inadequate meeting and conference facilities, and problems associated
with the use of residential accommodation as office space.[5]
2.6
A revision of the 2003 report undertaken in September 2005 confirmed the
earlier report findings.[6]
Scope
2.7
The proposed works encompass the following elements:
n demolition of the
existing temporary annex and two apartments;
n adding a three-level
extension to the main building of 2,400 square metres that will comprise new
office space and replacement office space lost through the demolition of the
annex and two apartments currently used as office space;
n refurbished and new
access control, security and secure communications systems;
n new office fit-outs
for the tenant agencies;
n new mechanical,
electrical and plumbing services (MEP) for the proposed extension, together
with upgrades where required of the existing MEP services within the main
chancery; and,
n essential
refurbishment of the mechanical, electrical, fire and standby power systems.[7]
2.8
The proposed works will require the relocation of some attached agencies
to temporary accommodation until completion of the project[8].
Project Delivery
2.9
DFAT proposes that the project will be delivered via a traditional style
of design, documentation, tendering and contracting process. DFAT considers
that this represents the best value for money for the Australian Government,
and allows the Department, as the building owner, to be fully in control of all
the project delivery stages.
2.10
A single contract will be awarded for the construction works and the
fit-out works. Tenders will be called from a selected list of contractors,
short-listed on the basis of pre-qualifications received.
The advertising for pre-qualifications
will be called both in Australia and China.
2.11
Under the master control program the design development phase will be
completed in December 2007. Tendering is programmed for January 2008,
construction planned in September 2008; practical completion in October 2010,
with Final Certificate at the end of the defects period in October 2011.[9]
Cost
2.12
The estimated project cost is $21.61 million, based on August 2005 costs
escalated to construction. The estimate includes:
n construction costs;
n fit out works;
n project management
including design and site management;
n consultancy services,
including supervision;
n site office overheads;
n temporary relocation
costs; and,
n project allowances
including construction contingencies and an escalation provision.[10]
2.13
It does not include:
n furniture;
n artworks; and,
n white goods.[11]