Chapter 2 The Proposed Works
Purpose
2.1
The ACS has a number of current leases due to expire around 30 June 2009, and proposes to collocate all staff into a single new building at The
Circuit, Brisbane Airport, Queensland.[1]
2.2
The proposed works are expected to realise a number of operational and
administrative efficiencies that include:
n a cost effective
property solution, with lower energy consumption and improved environmental
initiatives;
n advantages from
technological improvements in building services;
n efficiencies in
infrastructure, eg training facilities, staff amenities, conference/ meeting
facilities and floor layout;
n inclusion of ACS
requirements into base building, eg security, air-conditioning and other
services;
n improved provision
for public contact, with the majority of public contact occurring on the ground
floor;
n minimisation of the
costs of internal churn by adopting an open plan office fit-out; and
n an ability to
flexibly deploy staff and consolidate operational activities due to the close
proximity to other ACS business units.[2]
Need
2.3
The ACS requires the provision of office-based accommodation that can
accommodate the specialist function areas that meet the objectives and
operational requirements of Service. These specialist function areas include a
public counter, data centre, investigation facilities, an armoury and detained
goods store, including dangerous goods storage.[3]
2.4
The ACS currently has a number of leases and memorandums of
understanding with other Federal Agencies of associated with existing ACS
premises in and around the Brisbane metropolitan area that expire on or around
30 June 2009, and is keen to avoid delaying the construction of the
base-building in order to avoid costs associated with the need to extend
current leasing arrangements beyond 30 June 2009. Subject to Parliamentary
approval the ACS intends confirming with the Brisbane Airport Corporation that
construction of the building should proceed.[4]
Scope of the Work
2.5
The works include the fit-out of a four (4) storey office building with
a net lettable area (NLA) of approximately 9000 square metres and each floor
having an area of approximately 2400-2800 square metres.[5]
2.6
In addition it is proposed to provide 29 new visitor parking spaces and
parking for 60 operational vehicles. There will also be an external enclosed
four vehicle garage for mobile x-ray vehicles.[6]
2.7
The works to be undertaken include:
n The integration of
all electrical, mechanical, communications, security, fire and hydraulic
services into the base building works; and
n Architecturally
designed office accommodation that will include:
- the
construction of a public counter;
- general
office areas;
- a
computer facility;
- meeting
rooms;
- utilities;
- storage
space;
- kitchens;
- a first
aid room;
- carers/family
facility; and
- conference
and training spaces.[7]
2.8
In addition provision has also been made for a gymnasium and showers and
change rooms.[8]
Project Delivery
2.9
The ACS proposes engaging the services of consultants, project managers,
contractors and suppliers to undertake the work that will be overseen by a
fit-out project team established to deliver the project. The project team will
include the Manager Accommodation Projects, an independent project manager,
design consultants, a quantity surveyor and other experts as required.[9]
2.10
The BAC is expected to begin construction of the base building in
October 2007 with a completion date scheduled for March 2009. The fit-out
procurement process will commence during the period September to November 2008.[10]
2.11
The Design Construction and Lease Agreement will allow ACS to commence
fit-out works from 1 January 2009, with works continuing until May 2009. Staff
occupancy will commence effective from 1 July 2009.[11]
Cost
2.12
The estimated cost of this proposal is $15.84 million based on a fit out
and provision of services of approximately 8,100 square metres. This estimate
also includes:
n An amount of $1.4
million for the fit-out of a future expansion area of 855 square metres;
n an escalation of 9per
cent;
n an allowance for
consultancy costs;
n authority fees and
charges;
n base building
modifications;
n fit-out building
works;
n furniture, fittings
and equipment;
n contingency
allowances; and
n relocation costs.[12]