Chapter 6 Auditor Report No. 20 2009-1 The National Broadband Network
Request for Proposal Process
Introduction[1]
6.1
In March 2007, the Australian Labor Party (Labor) released its broadband
election policy to increase broadband internet speeds for 98 per cent of
Australians by up to forty times. Labor considered that its national broadband
network (NBN) would deliver significant national economic benefits and new
services for the benefit of many consumers, particularly those in rural and
regional areas. Labor committed that, in government, it would:
- partner with the
private sector to deliver a fibre-to-the-node (FTTN) NBN over five years to 98
per cent of the population with minimum speeds of 12 megabits per second
(Mbps);
- within a six-month
timeframe, undertake a competitive assessment of proposals from the private
sector to build the network;
- ensure competition in
the sector through an open access network that provides equivalence of access charges
and scope for access seekers to differentiate their product offerings;
- put in place
regulatory reforms to ensure certainty for investment; and
- make a public equity
investment of up to $4.7 billion.[2]
6.2
To meet the new Government’s tight timeframe, the then Department of
Communications, Information Technology and the Arts (now the Department of
Broadband, Communications and the Digital Economy (DBCDE or the department))
provided early advice to the Government on the implementation of its broadband
election commitments. The Government agreed in January 2008 to conduct a
Request for Proposal (RFP) process to select a proponent(s) to build, operate
and maintain the NBN. The Government’s broadband policy reflected its election
commitments, but broadened the technology choice to any fibre-based solution
(using FTTN or fibre-to-the-premises (FTTP) architecture). Further, it did not
specify a preferred form for the Government’s investment in the network, that
is, the contribution could have been as an equity investment or some other form
of funding. In parallel with the NBN RFP process, the Government invited
proponents, industry and public interest groups to provide submissions to the
Commonwealth on regulatory issues associated with a fibre-based network, including
consumer safeguards.
6.3
There was significant public and industry interest in the NBN RFP
process and its potential outcome. The department assessed the potential for
litigation during the process and at its conclusion as high. Consequently, the
department identified the need for the process to be conducted within a strong
probity framework and for decisions to be informed by appropriate specialist
advice. In the first half of 2008, the department progressively engaged
specialist advisers to assist in developing and conducting the RFP process,
including: probity adviser; investment, financial and commercial adviser;
technical adviser; legal adviser; and regulatory economic adviser.
6.4
On 11 March 2008, the Minister announced the membership of the Panel of
Experts (Panel), chaired by the department’s then Secretary, that would assess
the NBN proposals and put forward recommendations to the Minister for the
preferred proponent(s). The Minister also invited industry and public
submissions to assist in the development of the RFP document. The RFP document
was approved by the Minister and released on 11 April 2008. The document
expressed the Government’s broadband policy parameters as criteria against
which proposals would be assessed, rather than as mandatory requirements. The
RFP sought both national proposals and State/Territory-based proposals,
covering individual States or Territories, as part of a national solution.
Potential proponents were required to meet pre-qualification requirements by 23
May and lodge proposals by 25 July 2008. A subsequent addendum to the RFP
process extended the closing date to 26 November 2008.
6.5
Eight parties met pre-qualification requirements[3],
although one party subsequently withdrew. The department and the proponents
held four rounds of bilateral meetings between June and November 2008 to
outline the progress of proposal development, and to clarify aspects of the RFP
process and its requirements.
6.6
On 26 November 2008, proposals were received from six proponents – four
national proposals and two State/Territory-based proposals. The national
proposals generally put forward FTTN as the principal technology for providing
connections to premises. The department determined that five of the six
proposals met the RFP’s minimum conditions for participation, and these
proposals proceeded to the assessment phase. Telstra’s proposal was excluded from
the RFP assessment process because it did not meet minimum conditions for
participation. The proposal did not include a Small and Medium Enterprise (SME)
Participation Plan.[4]
6.7
On 20 January 2009, the Panel’s Evaluation Report to the Minister
advised that the three remaining national proposals had been assessed in
accordance with the RFP document and that none offered value for money for the
Commonwealth. The panel further concluded that there was no prospect that the
proponents would be able to refine their proposals sufficiently to provide
value for money. As a consequence, and in accordance with the RFP document, the
Panel’s assessment of State/Territory-based proposals did not proceed beyond a
preliminary review. In conjunction with its Report, the Panel submitted
separate advice to the Minister on how the Government’s objectives might be
achieved outside the parameters of the RFP. Its primary proposition was that
FTTP was a preferable, albeit more costly, technology to FTTN, and that the
Government should explore incentive schemes to encourage the roll-out of FTTP.
6.8
On 7 April 2009, the Minister terminated the RFP process. All proponents
were immediately advised of the Minister’s decision and the Government’s new
policy approach. The Prime Minister, the Treasurer, the Minister for Finance
and Deregulation and the Minister jointly announced the establishment of a new
company to build and operate a new super-fast NBN (National Broadband Network
Company Ltd). At the same time, the Minister released the Panel’s observations
from the Evaluation Report. The Panel observed that each proposal contained
attractive elements and, collectively, they provided a good evidence base for
the Government to move its policy agenda forward. The Panel also observed that:
- proposals lacked
committed private sector funding;
- none of the national
proposals was sufficiently well developed to present a value-for-money outcome;
- no proposal submitted
a business case that supported the roll-out in five years of a NBN to 98 per
cent of Australian homes and businesses with a Government contribution of $4.7
billion;
- FTTN is unlikely to
provide an efficient upgrade path to FTTP;
- there was a risk of
liability to pay compensation to Telstra for exclusive or near-exclusive access
to Telstra’s customer access network; and
- proponents sought
excessive regulatory restrictions on competitors building and operating their
own fibre-based networks in competition with the NBN (that is, overbuild
protections).
6.9
The department offered oral debriefings to all proponents that met the
minimum conditions for participation and returned bid bonds to all proponents,
although there was some delay in one instance.
The Audit
Audit objective[5]
6.10
On 21 April 2009, Senator the Hon. Nick Minchin, then Shadow Minister
for Broadband, Communications and the Digital Economy, wrote to the
Auditor-General requesting consideration be given to conducting an audit of the
NBN RFP process. Issues raised included the outcome of the process; whether
amendments were made to the RFP documents relating to non-compliant bids; Telstra’s
exclusion from the process; the costs associated with the RFP process for both
the Government and bidders; and the refund of bonds paid to bidders.
6.11
After conducting a preliminary review, the Auditor-General decided to
undertake a performance audit into the NBN RFP process. The objective of the
audit was to examine key aspects of the process, including:
- the background to and
conduct of the RFP process;
- management of key
risks associated with the process and outcomes; and
- stakeholder
consultations.
6.12
The audit examined DBCDE’s management of key aspects of the:
- implementation of the
NBN RFP process from the time of the election of the new Government on 24
November 2007 to the release of the RFP document on 11 April 2008; and
- conduct of the NBN
RFP process after the release of the RFP document to the termination of the
process on 7 April 2009.
Overall audit conclusion[6]
6.13
Labor went to the Federal Election in November 2007 with a commitment to
create a national FTTN broadband network, with construction to begin by late 2008.
Following the swearing in of the new Government in December 2007, the
department gave priority to developing and implementing this election
commitment. The Government’s approach was to pursue a process that maximised
competitive tension between potential proponents and promoted innovation to
achieve the best outcomes and best use of up to $4.7 billion in government
funding. It has been generally acknowledged within the telecommunications
sector that this amount was the level of funding sought by Telstra from the
former Government in 2005 to upgrade its equipment to build a FTTN network
covering 98 percent of Australia’s homes and businesses at speeds of 12 Mbps.
6.14
After considering advice on the pros and cons of conducting the process
in one rather than two stages, the Government concluded that a one-stage
process was appropriate and its risks could be managed. The alternative,
adopting a multi-stage process, would have been the more conventional approach
for conducting tender processes of this size, nature and risk, particularly
when seeking innovative solutions. Proponents contacted by the ANAO considered
that the two-way dialogue an expression of interest stage in a two-stage
process generates, would have better informed the RFP process and the RFP
document, increasing the likelihood of a successful outcome. The main
disadvantage of multi-stage tendering is the additional time required to
approach the market, or particular proponents, more than once, which was a
factor considered by the Government given the tight timeline envisaged for the
assessment process.
6.15
The department identified the likelihood of many of the key risks to a
successful outcome to the RFP process when assisting the Government to settle
the details of its broadband policy, although some were not fully analysed at
the time. These risks included the sufficiency of government funding to attract
commercially-viable proposals capable of acceptance, the potential payment of
‘just terms’ compensation to Telstra for the compulsory acquisition of the
right to use its assets should a non-Telstra proposal be successful,[7]
and the uncertain regulatory environment. The primary means of addressing these
and other risks was to design the RFP process to maximise flexibility, minimise
mandatory requirements and allow proponents to offer innovative solutions.
6.16
National proponents were asked to submit binding proposals against the
18 Commonwealth objectives for the NBN and other evaluation criteria, and
outline the regulatory changes necessary to facilitate their proposals. The
process left open the prospect that a proposal may be acceptable even though it
did not meet all objectives and criteria. The competitive assessment process
was expected to determine the NBN that the market could build and operate.
Although the RFP document met the requirements of the Commonwealth Procurement
Guidelines (CPGs), there was insufficient time to fully address specialist
advisers’ concerns that a lack of detail in the RFP put at risk attracting
binding offers. Nevertheless, the RFP document was drafted so that it could be
varied to address risks and issues as and when they arose during the process.
6.17
Throughout the process, the department kept the Minister informed of
progress, including:
- updated appraisals of
most risks to the process, and the likelihood of a successful outcome;
- possible scenarios
including their likelihood and consequences; and
- summarised feedback
from proponents on the elements likely to feature in their proposals and the
challenges posed by the RFP.
6.18
After the announcement of the RFP process, potential proponents were
initially concerned that the proposed timeframe would be insufficient to
prepare and lodge fully developed proposals. However, the proponents considered
that their concerns were addressed when the RFP timeline was extended to allow
them time to consider carriers’ network information. Proponents advised that
the RFP’s flexibility gave them significant scope to submit eligible proposals
with innovative technical solutions. However, they found it difficult to
develop competitive and commercially-viable proposals that would be acceptable
to the Government, while not necessarily meeting all the objectives and other
criteria.[8]
6.19
Proponents requested guidance on the relative importance of the
Commonwealth’s objectives, evaluation criteria and the regulatory changes that
would (or would not) be accepted. However, as the Government had no determined
preference for the NBN within its stated objectives, further advice on these
issues was not forthcoming beyond that included in the RFP document. As a
consequence, proponents found the bilateral meetings with the department and
its specialist advisers of limited value. State/Territory-based proponents
considered that the late clarification of the way their proposals would be
assessed under the RFP disadvantaged their proposals and, if received earlier,
may have influenced their decision to participate in the RFP process.
6.20
The RFP document saw FTTP as the future platform of the network to meet
future customer demand and service developments to at least 2020 and beyond.
However, after the RFP had been issued, the department received unsolicited
advice from the Australian Competition and Consumer Commission that FTTN was
not a stepping stone towards FTTP. Most FTTN expenditure would be on equipment
that becomes obsolete under a FTTP network platform. A FTTN network could also
serve to delay FTTP if the successful proponent was not under significant
competitive pressure and could therefore delay further investment until they
had fully recovered their initial investment.
6.21
As the RFP open period progressed, it became increasingly obvious to the
department that the likelihood of a successful outcome was reducing. Initially,
the department and its advisers considered offers capable of acceptance,
necessitating some form of ‘second stage’. In mid-August 2008, the department first
noted possible options for progressing the Government’s broadband policy
within, subsequent to, or outside of, the RFP process. By late-October 2008 and
prior to the RFP closing date, alternative methods of delivering the
Government’s broadband policy began to be looked at more formally, should the
RFP process not result in any acceptable proposals. By this time, it had become
apparent that:
- the global financial
crisis was having an adverse impact on proponents’ ability to attract funding
for their investment in the NBN;
- Telstra was seeking
certain assurances from Government, including in relation to the confidentially
of its bid information and potential regulatory solutions, before committing to
lodging a proposal;
- some members of one
pre-qualified consortia announced their withdrawal from the consortia; and
- non-Telstra
proponents were unlikely to propose a national technical solution that would
not require Telstra’s equipment, or submit a viable business model that took
into account potential compensation to Telstra of some billions of dollars for
the compulsory acquisition of the right to use its equipment.[9]
6.22
Although not guaranteeing a successful outcome, the flexibility within
the RFP process meant that the Government could have varied the RFP document
and process when it became apparent that:
- proponents were
looking for clearer direction and were unlikely to submit proposals that met
all the Commonwealth’s objectives and other evaluation criteria; and
- the global financial
crisis was affecting the proponents’ ability to finance their proposals.
6.23
Proponents would have had an opportunity to submit better developed and
more competitive proposals had they received:
- greater clarity as to
how the information requested was to be used when assessing proposals against
the RFP’s multiple objectives and criteria;
- guidance as to the
relative importance of the evaluation criteria and Commonwealth’s objectives;
and/or
- a clearer
understanding of the Government’s regulatory intent for the NBN.
6.24
Providing the clarity and guidance proponents sought would most likely
have necessitated an extension to the Government’s timetable for the RFP
process.
6.25
The NBN evaluation plan, which was approved by the Panel and the
Minister before the closing date for proposals, comprehensively set out the
assessment process and aligned with the RFP document. Nevertheless, its
development proved to be a complex and time-consuming exercise. The Panel,
assisted by the department, specialist advisers and other Australian Government
departments and agencies, assessed NBN proposals in accordance with the
evaluation plan. The then Secretary’s decision to exclude Telstra’s 12-page
proposal from the assessment process was informed by comprehensive legal
advice. The Panel assessed the remaining national proposals against the six
evaluation criteria and determined that nearly all criteria were either met to
a marginally acceptable standard or failed.
6.26
The ANAO found that conclusions and recommendations in the Panel’s
Evaluation Report were supported by appropriate evidence. The Panel’s published
observations of the process generally represented the reasons for the
non-selection of a national proponent, as well as providing some advice to the
Government on policy options for going forward. In separate advice to Government
at the conclusion of the Panel’s role in the RFP process, the Panel identified
FTTP as the preferred technology for the NBN. Although more expensive, the
Panel identified a number of ‘hidden’ costs in FTTN proposals, including
potential compensation to Telstra, risk of obsolescence and reduction in
competition through requested regulatory changes.
6.27
The Government’s choice of a fibre-based technology platform for the NBN
and the quantum of government funding available to the successful proponent(s)
meant that Telstra’s assets, including its customer access network and ducts
from the exchange, were a critical dependency for the success of the NBN RFP
process. It was generally accepted that the only other technology for a
national fibre-based network, FTTP, would require a significantly greater
government contribution to be commercially viable. Analysis by DBCDE as the RFP
progressed determined that, although a FTTN network could co-exist with
copper-based broadband networks, the amount of government assistance on offer
meant it was unlikely to be commercially viable for reasons that included its
ability to attract enough customers to cover its costs and that it would still
require access to Telstra’s customer access network.
6.28
As a consequence, Telstra was inherently well-placed to lodge a
competitive (and potentially successful) proposal. Non-Telstra proposals were
likely to present significant risks, including:
- the payment of
substantial levels of compensation to Telstra for the compulsory acquisition of
the right to use its assets; and
- potential regulatory
changes that would restrict other entities (mainly Telstra) building a parallel
fibre-based broadband network (which could be inconsistent with Australia’s
international trade obligations, and therefore at odds with the Government’s
broadband policy).
6.29
Despite the RFP process’s complexity and short timeframe, the ANAO found
that the Panel and the department conducted the formal process well, within the
parameters of the Government’s broadband policy and in accordance with the
CPGs. As the RFP process progressed, the department advised the Minister that
the prospects of a successful outcome were reducing. At the end of the RFP
process, there were no successful proposals.
6.30
The RFP process has come at a significant cost to the Government and
proponents, with costs incurred being in excess of $30 million. DBCDE’s costs
were some $17 million and the proponents’ costs (where advised) ranged between
$1 million and $8 million. In reviewing the process employed and in light of
the outcome, the ANAO made a number of observations:
- early in the process,
most NBN stakeholders considered that a two-stage process to select
proponent(s) for the NBN would have improved the prospects of a successful
outcome and may have reduced proponents’ costs;
- requesting proponents
to outline their preferred regulatory environment for their NBN was unusual for
an RFP process and made a complex commercial transaction considerably more
complicated;
- the global financial
crisis significantly reduced the prospects of a successful outcome by affecting
the viability of the proposed NBNs; and
- using FTTN technology
for the network limited its potential scalability.[10]
6.31
The department informed the ANAO that the Government was made fully
aware of all of the key risks and their significance for a successful outcome
to the RFP process. The ANAO found that while it is the case that the key risks
and their broad significance were identified in early advice to the Government,
the department did not fully assess the consequences of some of these risks
until relatively late in the RFP process. These included, in particular, the
possible magnitude of: the potential payment of compensation to Telstra should
a non-Telstra proposal using FTTN technology be successful; and the
consequences for investment in FTTN equipment, which largely would become
obsolete, should the network be upgraded to FTTP technology. The design of the
Government’s approach to the market would have been better informed had the
department provided timely advice on these issues ahead of the RFP process
being settled.
6.32
As it was, the Government decided to seek binding offers from the market
through a one-stage RFP process and give proponents wide scope to request
regulatory changes to facilitate their proposals. This approach was not
conventional for a competitive assessment process of this size, nature and
risk. Given the amount of government funding on offer, Telstra was the
proponent most likely to be in a position to build and operate a viable fibre-based
NBN. The likely impact on the prospects of a successful RFP outcome had Telstra
lodged an eligible proposal, is indeterminate. As the outcome of the RFP
process showed, no other proponents were successful either.
6.33
The audit did not make any recommendations to the department as the RFP
process had been finalised. Nevertheless, the audit emphasises the importance
of departments gaining, as early as possible, a sound understanding of the
implications of those risks that are critical to the success of major tender
processes, amongst the many risks that are required to be managed. This is
particularly challenging in a one-stage process that is seeking binding offers.
The Committee’s review
6.34
The Committee held a public hearing on Thursday 11 March 2010, with the
following witnesses:
- Australian National
Audit Office (ANAO); and
- Department of
Broadband, Communications and the Digital Economy (DBCDE).
6.35
The Committee took evidence on the following issues:
- identification and
evaluation of risk;
- specialist advisers;
- the reducing
likelihood of a successful outcome;
- options to change
RFP;
- Telstra’s bid; and
- lessons learned.
Identification and evaluation of risk
6.36
The ANAO found that the DBCDE had conducted the RFP process well, within
the parameters of the government’s broadband policy and in accordance with the
Commonwealth’s procurement guidelines.[11] The ANAO also found that
the department identified the ‘key risks and their broad significance ‘early in
the process and advised the Government accordingly.[12]
However, the ANAO found that the department had not assessed the impact of two
of those risks until relatively late in the process:
- the potential payment
of compensation to Telstra should a non-Telstra proposal using FTTN technology
be successful; and
- the consequences for
investment in FTTN equipment, which largely would become obsolete, should the
network be upgraded to FTTP technology.[13]
6.37
The ANAO identified the first of these, the amount of compensation that
may have to be paid to Telstra, as a significant key risk. While the ANAO
acknowledged that the department had kept the Minister and the Government fully
informed of the possibility of this risk throughout the process, it considered
that an attempt should have been made earlier in the process to quantify the
risk.[14] The ANAO maintained
that:
… earlier advice to Government on the possible magnitude of
the potential Telstra compensation would have provided the Government with a
greater appreciation of the consequence of this key risk, including its
relativity to the likely cost of the network, and potential impact on a
successful outcome. This information would have better informed, and may have
influenced, the Government’s approach to delivering the NBN.[15]
6.38
In its written response to the Audit Report the DBCDE said that
estimating a compensation figure early in the process was problematic for a
number of reasons:
Until there was some measure of clarity as to both the
intended approach of non-Telstra proponents to utilising Telstra infrastructure
and to the proposed arrangements to recompense Telstra for that use, meaningful
compensation estimates could not be developed.[16]
6.39
The Committee requested further explanation as to why DBCDE were
reluctant to quantify the risk earlier and provide more specific advice to the
Government. The department defended its position, telling the Committee that,
in hindsight, it is easy to speculate that the process could have been handled
differently but at the time a reliable compensation assessment could not be
undertaken until the proposals were received.[17] To have any level of
accuracy, a compensation estimate would have to take into consideration what
proponents were proposing:
… it was very difficult to assess the compensation without
fully understanding the extent to which proponents were proposing to make use
of Telstra’s network and the extent to which they were proposing to pay Telstra
for using that infrastructure. We certainly had proponents who were
representing to us that they considered that they were intending to pay Telstra
for access to their infrastructure [an amount] that would be sufficient to
mitigate their compensation risks and we had other proponents who were indicating
to us that they had technology solutions that meant that the compensation would
not become payable because it would not be a mass cutover, so it would be done
on a customer choice basis.[18]
6.40
The Committee asked at what date DBCDE were able to quantify the compensation
risk to Telstra. The Department told the Committee that in September 2008 the
direction being taken by non-Telstra proponents was becoming clearer and
Frontier Economics was able to develop ‘preliminary estimates of the ranges of
compensation that might be payable to Telstra’ under a variety of scenarios.[19]
6.41
The Committee acknowledged that the Department had informed the Minister
of the potential risk posed by a compensation payment to Telstra in the
Department’s Incoming Government Brief and continued to scrutinise this area of
risk at regular briefings with the Minister.[20] However, the Committee asked
when the Minister had been advised of the possible amount of the compensation
risk and DBCDE informed the Committee that the advice from Frontier Economics
was ‘incorporated in subsequent documents and presentations prepared for the
Minister’ after the Department received the report in September 2008.[21]
Specialist advisers
6.42
The ANAO found that DBCDE had engaged a number of specialist advisers to
provide ‘commercial, technical, economic, regulatory and legal advice during
the competitive assessment process for the NBN’ in line with the Commonwealth
Procurement Guidelines (CPGs).[22] However, the ANAO noted
that the advisers were not appointed until mid-March 2008.[23]
The ANAO points out that this was less than one month before the release of the
RFP and allowed little time for the draft RFP document to be scrutinised by the
specialist advisers or the department to revise the document in light of the
advisers’ comments.[24]
6.43
The Committee expressed concern that the lack of timely expert appraisal
may have adversely affected the advice provided to government, particularly
with regard to risk. The ANAO suggested that the delay in appointing the expert
advisers may have contributed to not providing risk assessment earlier and considered
that DBCDE could have sought outside expert legal advice earlier, specifically
on the compensation risk to Telstra.[25] Such an expert could
have drawn on available information to provide an estimate to Government that
‘could have been updated over time when better information became available on
compensation factors’.[26]
6.44
The Department maintained that there was sufficient expert advice
available but conceded that the timeframe was shorter than normal for an RFP
process.[27]
Reducing likelihood of a successful outcome
6.45
The Committee asked the ANAO when, from the audit, it had become clear
that the RFP process would not produce a successful outcome. The ANAO replied
that the Department had informed the Minister in July 2008 that there may need
to be more that one stage to the process and that:
… in mid-August (2008) the department first noted there were
possible options they were putting forward. By late October (2008) alternative
methods were being looked at as to how the process may continue …[28]
6.46
The Committee asked DBCDE to clarify why the process was continued after
July 2008 when it became clear that the chance of a successful outcome was unlikely.
The Department explained that at that stage a bid from Telstra was still possible
which could provide a successful outcome and that:
… the minister had a view that notwithstanding that there was
a chance that it would not result in a successful proposal that he wanted the
process to continue so that we actually could test the market.[29]
6.47
The ANAO added that the process had not ‘failed’ even though there had
been no successful tenderer as:
The process was followed in accordance with the Commonwealth
procurement guidelines. The evaluation was done correctly, the process was done
correctly. There was no successful outcome, because none of the proponents met
the criteria or the objectives.[30]
Options to change RFP
6.48
In light of the reducing likelihood of a successful outcome, the
Committee asked DBCDE if it had considered changing the RFP. The department
said it had the flexibility to amend the process but that such change presents
problems as it can have a significant impact on proponents.[31]
DBCDE explained that, if such a change is contemplated, the proponents would
need to be invited to ‘discuss the possibility of amending the process and ask[ed]
for impact assessments’.[32]
Telstra’s bid
6.49
The Committee asked the ANAO if the risk of Telstra not submitting a
proposal had been identified and, if so, at what stage of the process. The ANAO
found that early in the process there was an expectation that Telstra would
lodge a proposal. It was not until approximately one month before the closing
date for submissions that DBCDE became aware that Telstra ‘may decide to
withdraw from the process’.[33]
6.50
DBCDE noted that Telstra did put in a proposal but that the proposal did
not meet the minimum mandatory requirements and was subsequently excluded from
the process.[34] The Committee queried
whether or not Telstra had been asked why it had submitted an incomplete
proposal. DBCDE told the Committee that, as the Telstra proposal did not comply
with the minimum mandatory requirements it was not assessed.[35]
The Department added that it had taken legal advice from six separate sources
before making the decision to exclude the proposal.[36]
Lessons learned
6.51
The Committee asked the ANAO what lessons could be learned from the NBN
RFP process with regard to mitigating both foreseen and unforeseen risks. The
ANAO reaffirmed the findings of the audit, emphasising the need for early
identification of risks:
… the importance of departments gaining, as early as
possible, a sound understanding of the implications of those risks that are
critical to the success of major tender processes, amongst the many risks that
are required to be managed. This is particularly challenging in a one-stage
process that is seeking binding offers.[37]
6.52
The Committee asked DBCDE if it had undertaken a review in light of the
audit findings and if there had been any changes to protocols. The Department
reiterated that the audit report had found that DBCDE had run the process well,
conforming to the Commonwealth Procurement Guidelines. DBCDE added that it has
held discussions with other departments and with the Auditor-General regarding
the difficulties inherent in varying a process once it has begun:
I have said to the agencies involved that the greatest difficulty
we have here is the need to effectively [give] permission to take risk. It is
actually risk inside the process. … if part of the way through the process you
think, ‘It’s a judgement call but it’s likely that the proponents will (not be)
able to satisfy us, should we pull the plug, should we vary it?’ that is
actually a very difficult proposition because of the response of proponents. In
other words, one or two proponents might be very happy for you to alter this
and others will be very angry with you.[38]
Conclusion
6.53
Considering the size of the budget for this project and the apparent
lack of a positive outcome, the Committee shares the ANAO concerns regarding
risk management for the project. The Committee encourages all agencies and
departments to ensure that risks are identified early in the tender process
and, where possible, quantified.