Key points
- The Ranger Uranium Mine was established in an area known as the Ranger Protected Area (RPA) in 1979, on the Country of the Mirarr Traditional Owners, without their consent.
- The mine has been owned and operated by Energy Resources of Australia Limited (ERA) (a subsidiary of Rio Tinto Group) since 1980.
- Operations at the Ranger Uranium Mine ceased on 8 January 2021 and ERA has commenced rehabilitation activities.
- The existing Section 41 Authority, granted under the Commonwealth Atomic Energy Act 1953 (AE Act), requires ERA to rehabilitate the RPA in accordance with specified Environmental Requirements by 8 January 2026. The RPA would then be returned to the Mirarr Traditional Owners, with a view to incorporation of the area into the surrounding Kakadu National Park.
- ERA has advised that rehabilitation activities will not be completed by that date, due to emergent technical risks and the need for additional works.
- Key stakeholders agree that the deadline should be extended to allow rehabilitation activities to be completed.
- The Bill amends the AE Act to provide two regulatory options for ensuring that ERA continues to be required to complete all proposed rehabilitation and monitoring activities in accordance with the Environmental Requirements. These are (i) the establishment of a new Rehabilitation Authority, and (ii) the variation of the existing Section 41 Authority. The Bill also provides for the progressive close-out and return of parts of the RPA.
- The Bill allows an unlimited number of Rehabilitation Authorities to be granted. While this allows flexibility in light of the unique circumstances of the rehabilitation and monitoring activities, it also leaves uncertainty as to a final deadline for the completion of rehabilitation activities.
- The Bill is solely focused on rehabilitation and closure; it does not permit a resumption of mining activity and does not change the existing Environmental Requirements or required standard of rehabilitation.
Introductory Info
Date introduced: 8 September 2022
House: House of Representatives
Portfolio: Industry, Science and Resources
Commencement:: The day after Royal Assent.
Purpose and
Structure of the Bill
The Atomic
Energy Amendment (Mine Rehabilitation and Closure) Bill 2022 (the Bill)
amends the Atomic
Energy Act 1953 (the AE Act) to preserve the existing regulatory
framework that applies to the Ranger Uranium Mine (Ranger) in the Northern
Territory to ensure that the Mine Operator completes the rehabilitation
activities in accordance with the established Environmental Requirements.
The Bill is comprised of one Schedule, which is divided
into two Parts:
- Part
1 amends the AE Act by adding new definitions and amending existing
provisions and adding new provisions to Part III of the Act. These are
summarised as follows:
- Division
1: existing section 41 is amended to allow for a s.41 Authority to authorise
the carrying out of rehabilitation, remediation and monitoring operations and
to extend the period in which the authority may be in force
- Division
2 adds new sections 41CA to 41CG to provide for a new rehabilitation authority
to be issued
- Division
3 adds new sections 41CH to 41CI to provide for the progressive close-out of an
area covered by a Part III authority
- Division
4 adds new sections 41CJ to 41CS to provide for the variation and revocation of
a Part III authority
- Division
5 adds new sections 41CT to 41CY to clarify certain matters, including that matters
covered by a Part III authority are exempt from the provisions of Part 3 of the Environment
Protection and Biodiversity Conservation Act 1999 (EPBC Act)
- Division
6 amends existing offence provisions and clarifies matters relating to
compensation for acquisition of property.
- Part
2 contains application provisions.
Background
The Ranger Uranium Mine was established in 1979 in the
Ranger Project Area (RPA), an area of 78 square kilometres located approximately
260 kilometres south east of Darwin. The uranium deposits were discovered a
decade earlier, in October 1969, with further drilling confirming the
feasibility of mining the ore bodies known as ‘Ranger 1’ and ‘Ranger 3’.[1]
A Commission of Inquiry (the Fox Inquiry) was established
in July 1975 under the Environment
Protection (Impact of Proposals) Act 1974 (subsequently repealed and
replaced by the EPBC Act) to examine the environmental, social and
nuclear non-proliferation implications of mining at Ranger.[2]
The Inquiry issued two reports in 1976 and 1977, concluding:
The hazards of
mining and milling uranium, if those activities are properly regulated and
controlled, are not such as to justify a decision not to develop Australian
uranium mines.[3]
The Inquiry also recommended:
Any development of
Australian uranium mines should be strictly regulated and controlled.[4]
The Fox Inquiry was also empowered to determine the merits
of a claim by Traditional Owners to land in the Alligator
Rivers Region (ARR), including the RPA, under the then newly enacted Aboriginal Land
Rights (Northern Territory) Act 1976 (ARLA).[5]
The Inquiry recommended recognition of certain land in the ARR as Aboriginal
land.[6]
An area including the southern half of the RPA was granted to the Kakadu
Aboriginal Land Trust in September 1978, while an area including the northern
half of the RPA was granted to the Jabiluka Aboriginal Land Trust in November
1986.[7]
The RPA is situated on the Country of the Mirarr
Gundjeihmi Traditional Owners, for whom the area is of immense cultural
heritage significance.[8]
The mine was developed without their consent.[9]
In October 2015, the Mirarr Traditional Owners refused consent for mining
activities to continue beyond the existing project.[10]
The Mirarr Traditional Owners are represented by the Gundjeihmi Aboriginal Corporation (GAC). According
to the GAC, there have been ‘over 200 spills, leaks and breaches of licence
conditions ... in the four decades of the mine’s existence’, with a major incident
in 2013 resulting in the spilling of 1,400 m3 of slurry containing
ground uranium ore, water and sulphuric acid into the processing area.[11]
First Nations organisations, including the Northern Land
Council (NLC) and the GAC, have received royalties and other payments
associated with the operation of the mine.[12]
The Fox Inquiry also recommended that a major national
park be established in the ARR, subject to the exclusion of the Ranger
Protected Area and other areas where mining could proceed.[13]
Stage one of Kakadu National Park was proclaimed on 5 April 1979, and in October
1981 was inscribed on the World Heritage List for its outstanding universal natural and
cultural values.[14]
The National Park and corresponding Listing have subsequently been expanded.
The Listing notes ‘the future potential effects on the park of current uranium
mining will require ongoing scrutiny’.[15]
In 1999, the World Heritage Committee considered, but declined to add, Kakadu
to the List of World Heritage in Danger due to concerns about uranium mining and
milling and its cultural and environmental impacts on the values of the site.[16]
Energy Resources of Australia Limited (ERA), a public
company listed on the Australian Stock Exchange, became the owner and operator
of the Ranger Uranium Mine in 1980. ERA was acquired by the Rio Tinto Group in
2000.[17]
Mining activities commenced in 1981 and continued until 2012, whereafter
processing of stockpiled ore continued until 8 January 2021. Under its current
authority, ERA is required to rehabilitate the RPA in accordance with
Environmental Requirements by 8 January 2026.
A summary of other uranium mines and prospects, and
progress towards rehabilitation, in the Alligator Rivers Region is provided in
Appendix 1.
Legislative
framework[18]
Uranium mining in the Northern Territory (NT) is regulated
jointly by the Commonwealth and Northern Territory Governments. Day-to-day
management is delegated to the NT Government and given effect under the NT Mining
Management Act 2001; the responsible NT Minister must act in accordance
with the advice of the responsible Commonwealth Minister.[19]
For the purposes of this Digest, we focus on Commonwealth legislation.
Atomic
Energy Act 1953
The primary focus of the Atomic Energy Act
1953 (AE Act) in its initial form was to consolidate
Commonwealth control over nuclear materials, such as uranium, and technology.[20]
The Act vests ownership of uranium in the territories in the Commonwealth and
requires a person discovering uranium to notify the Commonwealth.[21]
The AE Act was amended in 1978 to authorise uranium
mining in the Ranger Project Area, giving effect to the Ranger Project
Agreement (see below).[22]
Specifically, an authority under section 41 (referred to as a s.41
Authority) may allow mining, recovery, treatment and processing of uranium.
Section 41A gives the Minister power to revoke an authority if satisfied that
the rehabilitation requirements have been met. Similarly, section 41C requires
the Minister to be satisfied with the conditions for ensuring the
rehabilitation of the site prior to granting an extension to the authority.
Aboriginal
Land Rights (Northern Territory) Act 1976
The Aboriginal Land
Rights (Northern Territory) Act 1976 (ALRA) creates a framework
for First Nations people in the NT to make land claims based on their
traditional connections to Country. Aboriginal land granted under the Act is
handed back by the creation of Land Trusts. The ALRA also creates Land
Councils—for example, the Northern Land
Council (NLC)—and provides ‘the legal framework for progressing social,
commercial and economic development activities on Aboriginal land on behalf of’
Traditional Owners.[23]
Part IV of the ALRA provides for the grant of mining
exploration licences on Aboriginal land.[24]
Exploration licences cannot be granted on Aboriginal land unless the Land
Council has consented or the Governor-General has declared that the national
interest requires the licence to be granted, and the prospective licence holder
has entered into an agreement under Part IV.[25]
The Land Council must consult with the Traditional Owners of the subject land
and any Aboriginal community or group that may be affected by the grant of the
licence.[26]
The Land Council may decide to consent to the grant of the licence if satisfied
that the traditional Aboriginal owners understand and agree to the terms and
conditions of the grant, and it has agreed the terms and conditions with the
applicant.[27]
An alternate process is provided where the terms and conditions of an agreement
are determined by arbitration (referred to as a s.44 Agreement).[28]
The ALRA specifically overrides the right of the
Traditional Owners of the Ranger Project Area to withdraw consent to mining
activity while a s.44 Agreement under the ARLA or a s.41 Authority under
the AE Act is in force.[29]
Environment
Protection (Alligator Rivers Region) Act 1978
The Environment
Protection (Alligator Rivers Region) Act 1978 (EP(ARR) Act)
established the statutory position of the Supervising
Scientist for the Alligator Rivers Region (ARR).
The role of the Supervising Scientist is held by the Assistant Secretary of the
Supervising Scientist Branch, within the Department of Climate Change, Energy,
the Environment and Water (DCCEEW). The Supervising Scientist, who is subject
to Ministerial direction, has four functions relating to the environmental
impacts of uranium mining in the ARR: research, supervision, monitoring, and
public assurance and advice.[30]
Environment is defined broadly, to include people and communities.[31]
The Supervising Scientist has limited compliance and enforcement powers[32]
and rather provides advice to the responsible Commonwealth and NT Ministers. The
Act also establishes the Alligator Rivers Region Advisory Committee, which
provides a forum for consultation.[33]
Environment
Protection and Biodiversity Conservation Act 1999
The EPBC Act provides the regulatory framework for
the assessment and approval of actions that may have a significant
impact on matters of
national environmental significance. These include actions that may have a
significant impact on world heritage area, and nuclear actions, including
decommissioning and rehabilitation of any facility or area in which mining or
milling uranium ore has been undertaken.[34]
As noted above, the Ranger Uranium Project was authorised
by the Commonwealth Government following a commission of inquiry (the ‘Fox
Inquiry’) under the Environment
Protection (Impact of Proposals) Act 1974. That Act was repealed and
replaced by the EPBC Act in 2000. Projects authorised under the former
Act may fall within the continuing use provisions of the EPBC Act,
subject to the activities covered by the specific environmental authorisation
and its renewal or extension.[35]
See ‘Key issues and provisions’ for further discussion of how the Bill seeks to
address the need for further assessment of rehabilitation of the RPA under the EPBC
Act.
Relevant
agreements and authorities[36]
The Ranger Uranium Mine was established following the
signing of the Ranger Project
Agreement on 9 January 1979 by the Commonwealth Government, the Australian
Atomic Energy Commission (AAEC), and the mining companies Peko-Wallsend
Operations Ltd and Electrolytic Zinc Company of Australasia Ltd.
The following Agreements and Authorities are annexed to
the Ranger Project Agreement:
- a
s.44 Agreement under the ARLA reached between the Commonwealth and the
Northern Land Council (NLC) on 3 November 1978
- a
s.41 Authority issued under the AE Act by the Minister for Trade and
Resources on 9 January 1979. Compliance with Environmental
Requirements is a condition of the Authority.[37]
On 12 September 1980, the 1979 Agreement was replaced by
the Government
Agreement as Amended. ERA accordingly acquired the interests of the parties
to the earlier agreement and became the owner and operator of the Ranger
Uranium Mine.[38]
The Government Agreement as Amended, s.44 Agreement, and
s.41 Authority were valid for 21 years, plus 5 years rehabilitation. Thus,
in 2000, an extension was needed to allow ERA to continuing mining operations.
In 1999, following several years of negotiations, the
Commonwealth Government and the NLC entered into a Deed (Extension Agreement)
extending the s.44 Agreement and requiring the parties to agree on a new s.44
Agreement.[39]
ERA also entered into a Mining Agreement with the NLC.[40]
In January 2013, the Mirarr Traditional Owners and ERA agreed to the terms and
conditions for a new (renegotiated) s.44 Agreement. The Gundjeihmi Aboriginal
Corporation describes the agreements as:
... provid[ing] the Mirarr and others with firmer and fairer
footing upon which to tackle the social disadvantage of Aboriginal people
across the region.[41]
The s.41 Authority under the AE Act was renewed on
14 November 1999[42]
and, together with the s.44 Agreement, runs for 26 years: 21 years mining with
activity to cease on 8 January 2021, and 5 years for rehabilitation activities
to be completed by 8 January 2026.
Scale of
the rehabilitation task
Rehabilitating the Ranger Uranium Mine has been described
as the most complex—and most expensive—mine rehabilitation project in
Australia’s history.[43]
The scope of works involves managing contaminated material, reinstating the
landform, and generating a functioning ecosystem. Based on a feasibility study
completed in 2019, ERA estimates:
- over
90 million tonnes of material will be moved to create the final landform
- haulage
trucks will work for 160,000 hours and travel 2.7 million kilometres over 36
months
- 47
plant species and 1.1 million plants will be planted in initial and infill
plantings
- on-going
monitoring and maintenance of the site will occur for 25 years once the
rehabilitation works are completed.[44]
Rehabilitation
requirements
Compliance with the Environmental
Requirements of the Commonwealth of Australia for the Operation of the Ranger
Uranium Mine (the Environmental Requirements) is a condition of the s.41 Authority
under the AE Act.[45]
The Environmental Requirements are also incorporated into authorisations
granted under the NT Mining
Management Act 2001.[46]
The Environmental Requirements cover matters including environmental protection,
rehabilitation, water quality, air quality, radiological protection, and the
storage, use and disposal of hazardous substances and wastes.
Relevantly, the rehabilitation objective requires that
ERA:
... rehabilitate the Ranger Project Area to establish an
environment similar to the adjacent areas of Kakadu National Park such that, in
the opinion of the Minister with the advice of the Supervising Scientist, the
rehabilitated area could be incorporated into the Kakadu National Park.[47]
ERA is also required to ensure that:
(i) the
tailings are physically isolated from the environment for at least 10,000
years;
(ii) any
contaminants arising from the tailings will not result in any detrimental
environmental impacts for at least 10,000 years ...[48]
The Environmental Requirements require ERA to prepare a
rehabilitation plan which must be approved by the Supervising Authority[49]
and the Minister, on the advice of the Supervising Scientist.[50]
The NLC must agree that rehabilitation activities meet the aim and objectives
for rehabilitation set out in the Environmental Requirements.[51]
ERA’s rehabilitation obligations come to an end over any part of the RPA when a
close-out certificate is issued by the Supervising Scientist, provided that the
Supervising Scientist and the NLC agree that the requirements have been met.[52]
ERA released its first Ranger Mine Closure Plan (RMCP) in
June 2018; it had been updated annually, with the most recent updated Mine
Closure Plan released in October 2020.[53]
The Supervising Scientist released an assessment of ERA’s
2020 Ranger Mine Closure Plan in December 2020, noting some improvement over
previous versions but concluding:
... the 2020 RMCP does not yet provide sufficient evidence to
demonstrate that the rehabilitation works proposed will satisfy the
Environmental Requirements.[54]
The assessment report notes that ERA is making some
progress on outstanding issues, while also noting that the Supervising
Scientist and ERA are yet to agree on some of the closure criteria.
ERA has not released a 2021 RMCP. In May 2022 ERA
commenced a feasibility study ‘in connection with a lower technical risk
rehabilitation methodology ... and to further refine the Ranger Project Area
rehabilitation execution scope, risks, costs and schedule’.[55]
The feasibility study is expected to take 12 months.
ERA is reported to have said that rehabilitation
activities ‘could drag on past the end of the decade’.[56]
It is important to recognise that the five-year
rehabilitation period from January 2021 to January 2026 contemplates physical
works; ‘full restoration of the natural ecosystems will take far longer’.[57]
ERA’s closure manager has indicated that development of a good ecosystem could
take about 25 years after planting, with natural regeneration taking longer. Notably,
the Supervising Scientist states:
In the years after
2026 an ongoing effort will be required to ensure that the rehabilitation is
successful. This will include: monitoring to ensure the rehabilitated site is
on a suitable trajectory towards closure and completion criteria and to detect
environmental impacts; the control of weeds and management of erosion; and, the
exclusion of fire during the early stages of vegetation establishment. Over
time, the requirement for post-rehabilitation management activities will reduce
until, eventually, the site no longer needs active management, at which point
it may be suitable for permanent closure.[58]
The Explanatory Memorandum to the Bill states that the
post-closure ‘monitoring period is estimated to be another 20 years’.[59]
Financial
provision for rehabilitation
A Ranger Rehabilitation Trust Fund has been established in
accordance with the Government Agreement as Amended.[60]
ERA is required to prepare an Annual Plan of Rehabilitation, the purpose of
which is ‘to determine the securities amount to be held by the Commonwealth
Government for Ranger rehabilitation obligations’.[61]
ERA is required to deposit monies into this Fund—or provide other
assurances—equivalent to the estimated costs of rehabilitation. As at 30 June
2022, $537 million was held in the Trust Fund and the Australian
Government held an additional $125 million in bank guarantees.[62]
On 2 February 2022, ERA informed the Australian Stock
Exchange that the estimated total cost of completing rehabilitation activities
had increased to between $1.6 billion and $2.2 billion (estimated at $526
million in 2017).[63]
Given the significant difference between estimated total cost of rehabilitation
activities and the amount currently provisioned, ERA states ‘an urgent interim
funding solution is required’.[64]
ERA’s most recent Annual Report states:
ERA has insufficient funds to fully fund its rehabilitation
obligation.
ERA is continuing to review all funding options. An inability
to obtain sufficient funding would have a material impact on ERA being able to
continue as a going concern. Rio Tinto has reiterated its commitment to
ensuring the rehabilitation of the Ranger Project Area is successfully achieved
to the appropriate standards. ERA is in ongoing discussions with major
shareholders about a funding solution.[65]
The Independent Auditor’s Report accompanying ERA’s Annual
Report notes ‘a material uncertainty exists that may cast significant doubt
on the Company’s ability to continue as a going concern’.[66]
In July 2022 Rio Tinto and ERA’s other major shareholders rejected an interim
entitlement offer which sought to raise $300 million.[67]
Rio Tinto’s Annual Report 2021 states that Rio has a closure provision
of $14.5 billion as at 31 December 2021, including an additional US$510 million
included due to the reforecast of the decommissioning cost for Ranger.[68]
Recent
inquiries and developments
In March 2019, the Senate Environment and Communications
References Committee completed a lengthy Inquiry
into Rehabilitation of Mining and Resources Projects as it Relates to
Commonwealth Responsibilities. The inquiry report notes that
‘regulation of mining and resources projects in Australia is primarily
undertaken at the state and territory level’, with the Commonwealth’s direct
role limited to projects subject to assessment and approvals under the EPBC
Act and certain uranium mines due to the Commonwealth’s historic
involvement in these projects.[69]
The Commonwealth may also have a role through intergovernmental agreements
under which the Commonwealth and states undertake to adopt a joint approach to
an area of environmental regulation.[70]
Submissions to the inquiry drew attention to variation in
state and territory frameworks, consideration of best practice rehabilitation
and the need for enforceable rehabilitation standards, episodes of
rehabilitation avoidance (instances where actions have been taken to avoid or
delay compliance with rehabilitation responsibilities), the adequacy of
financial assurance mechanisms and corporate reporting, and changing community
attitudes and expectations. The Committee was not able to reach agreement on a
unanimous set of recommendations.[71]
In 2021, the Commonwealth Offshore Petroleum
and Greenhouse Storage Act 2006 was amended to improve mechanisms for
dealing with decommissioning liabilities in the sector (estimated at $60
billion over the next 30 years).[72]
These measures—coupled with more proactive regulatory oversight—include enhanced
scrutiny of late-stage title and asset transfers, and expanded ‘call back’
powers whereby previous titleholders can be required to decommission infrastructure
and remediate the marine environment where the current or immediate former
titleholder is unable to do so (also known as ‘trailing liability’).
Separately, in 2021 a temporary industry levy was
introduced to recover the significant costs associated with the collapse of the
Northern Oil and Gas Group of Companies and decommissioning of the
Laminaria-Corallina oil fields.[73]
The levy was introduced to ensure that taxpayers would not be required to foot
the bill for the decommissioning activities.
Committee
consideration
Senate
Economics Legislation Committee
On 8 September 2022 the Bill was referred to the Senate
Economics Legislation Committee for inquiry and report by 23 November 2022.
Details of the inquiry are on the inquiry homepage at Atomic
Energy Amendment (Mine Rehabilitation and Closure) Bill 2022 [Provisions].
Senate
Standing Committee for the Scrutiny of Bills
At the time of writing, the Senate Standing Committee for
the Scrutiny of Bills is yet to consider the Bill.
Policy
position of non-government parties/independents
At the time of writing, there appears to have been no
comment on the Bill itself.
Position of
major interest groups
The Explanatory Memorandum states that entities with direct
interests in the operations at Ranger—namely ERA, Gundjeihmi Aboriginal Corporation,
NLC and the NT Government—
... provided feedback on three exposure drafts of the Bill,
and were also consulted throughout the policy development process.[74]
The Explanatory Memorandum notes that additional
consultation was undertaken with relevant Australian Government departments,
environmental NGOs, and the Minerals Council of Australia.[75]
ERA has described the present rehabilitation deadline
of 2026 a ‘key constraint’, and has called for amendments to the Act which
would extend ERA’s access to the Ranger Project Area.[76]
The Gundjeihmi Aboriginal Corporation and Environment
Centre NT have previously called on the Commonwealth Government to amend
the AE Act to extend the timeframe permitted for rehabilitation.[77]
The Gundjeihmi Aboriginal Corporation has indicated that
the unrealistic timeframe for rehabilitation was one reason it had refused to
support Ministerial approval of the 2020 Mine Closure Plan.[78]
In February 2022, a senior Mirarr Traditional Owner
welcomed greater transparency of the true cost of rehabilitation works, saying
this ‘reiterated the need for both industry and the Australian Government to
remain true to their commitments at Kakadu’.[79]
Environment Centre NT had expected amendments to be tabled
in Parliament in 2021; it has raised concerns that poor rehabilitation
decisions were being made due to time constraints.[80]
The Australian Conservation Foundation (ACF) has
raised concerns about the unrealistic timeframe for rehabilitation.[81]
Its joint report assessing ERA’s 2020 Mine Closure Plan raises numerous
concerns including:
-
a lack of clarity around the
post-closure regulatory framework and the oversight and accountability needed
to ensure compliance with the [Ranger Mine Closure Plan] and closure criteria
-
uncertainty over the adequacy of
current and future financing – especially in relation to post-closure site monitoring
and mitigation works
-
a lack of transparency around the
status and process for assessing the separate stand-alone applications for
significant aspects of the rehabilitation work.[82]
Financial
implications
The Explanatory Memorandum indicates that the Bill ‘has no
financial impact and applies to a single project and a single operator’.[83]
Existing provisions in the AE Act provide that the
Commonwealth is liable for loss or damage attributable to actions authorised
under a s.41 Authorisation.[84]
Statement of Compatibility with Human Rights
As required under Part 3 of the Human Rights
(Parliamentary Scrutiny) Act 2011, the Government has assessed the
Bill’s compatibility with the human rights and freedoms recognised or declared
in the international instruments listed in section 3 of that Act.[85]
The Government considers that the Bill is compatible with human rights because
‘to the extent that it engages human rights issues, it does so in a positive
way’.[86]
Specially, the Statement of Compatibility acknowledges an
adverse ‘impact on Traditional Owners’ access to traditional lands and right to
enjoy and benefit from culture’ due to the delayed return of the RPA to the
Traditional Owners. However, the Government considers that the Bill—by allowing
the Minister to preserve the Mine Operator’s legal requirement to rehabilitate
the RPA to the required environmental standard—will ‘ultimately support the
Traditional Owners’ right to self-determination and to enjoy and benefit from
culture’.[87]
Parliamentary
Joint Committee on Human Rights
At the time of writing, the Parliamentary Joint Committee
on Human Rights has not considered the Bill.
Key issues
and provisions
Part 1 – Amendments
to Part III
Part III of the Atomic Energy Act, headed ‘the
Ranger Project’, only concerns activities in the Ranger Project Area (as
described in Schedule 2 to the ARLA). This means that amendments to Part
III will not apply to questions of authorisation and rehabilitation of
uranium mining and milling projects elsewhere in Australia.
Definitions
Item 1 adds new definitions, including of Part
III authority. A Part III authority includes an authority issued under
section 41 or proposed section 41CA (that is, a Rehabilitation
Authority).
Variation
of an historic Section 41 Authority
Section 41 currently provides for the Minister to
authorise a person to undertake activities to mine or recover a prescribed
substance (including uranium).[88]
The authority may be subject to any conditions or restrictions the Minister
considers appropriate.[89]
Section 41A currently allows the Minister to revoke an authority, where
satisfied that the rehabilitation requirements have been completed, or to vary
an authority in limited circumstances.[90]
Section 41A would be repealed by Item 17 (see ‘Revoking a Part III
authority’ below).
The Bill proposes numerous amendments to section 41,
including to:
- omit
text in subsection 41(1) which provides a precondition to the Minister
authorising operations in accordance with a section 41 Authority[91]
- clarify
references to ‘land’ to ensure that an authority applies in relation to ‘the
whole, or a specified part, of the land in the Ranger Project Area’,[92]
thereby supporting progressive close‑out
- expand
the activities or operations that the holder of a section 41 Authority may be
authorised to do or carry out in the RPA (or part of the RPA) to include
operations relating to the protection, rehabilitation, remediation or
monitoring of the land[93]
- make
explicit that a section 41 Authority may impose conditions directly on the
authority holder, rather than specify conditions or restrictions on activities that
the authority holder is authorised to carry on[94]
- clarify
when a section 41 Authority may be varied or revoked, or terminates.[95]
In summary, the effect of the amendments would be that the
Minister would be empowered to vary or extend an existing section 41 Authority
and to add new conditions and restrictions relating specifically to rehabilitation.
A new Rehabilitation
Authority
Item 18 inserts a new Division 2 into Part 3 of the
AE Act, containing proposed sections 41CA to 41CG.
Proposed section 41CA allows the Minister to confer
on a person a new authority—a rehabilitation authority—to carry
on:
(a) specified
operations relating to the protection, rehabilitation, remediation or
monitoring of the whole, or a specified part, of the land in the Ranger Protected
Area;
(b) specified
operations of another kind in relation to the whole or a specified part, of the
land in the Ranger Project Area.[96]
Proposed sections 41CC, 41CD and 41CE provide
details of what may be authorised or required by a rehabilitation authority.
Rehabilitation requirements must be substantially similar to the existing
Environmental Requirements.[97]
The Bill references the Environmental Requirements by reference to the historic
section 41 Authority and does not, for example, propose including the
Environmental Requirements in regulation.
A rehabilitation authority may only be conferred if:
- the
Minister consults with the person—and that person agrees—with the proposed
terms of the authority, including authorised operations, the period for which
the authority is to be in force, any conditions or restrictions, and any
requirements that are to be imposed[98]
- a
section 44 Agreement under the ALRA is in force[99]
- the
Minister consults with the Land Council.[100]
There is no limit on the number of rehabilitation
authorities that may be conferred on a person.[101]
A rehabilitation authority remains in force for the period specified in the
authority, unless it is otherwise varied, extended, terminates or is revoked.[102]
Proposed section 41CB sets out who may apply for a
rehabilitation authority, and when. Applications can only be made by the holder
of the historic section 41 Authority (that is, ERA), or the hold of a
rehabilitation authority. The holder of a rehabilitation authority can however assign
their interests to another party.[103]
As the holder of the historic section 41 Authority,
ERA would be required to apply for a rehabilitation authority within 18 months
of the commencement of the Act, or such later time as determined by the
Minister.[104]
The Explanatory Memorandum notes that if ERA ‘fails to apply for a
Rehabilitation Authority within the specified timeframe, the Minister may vary
the historic Section 41 Authority under the provisions in Division 4’.[105]
The holder of a rehabilitation authority may apply for a
further rehabilitation authority at any time, but at least 12 months before the
authority is due to expire, or such later time as determined by the Minister.[106]
Progressive
close-out of the Ranger Protected Area
Item 18 also inserts a new Division 3 into Part III, with proposed sections 41CH and
41CI.
Proposed section 41CH provides that a Part III
authority may specify conditions under which a rehabilitation requirement is
taken to be satisfied (that is, completed). This may occur by:
(a) specifying
a procedure for determining when the requirement is taken to be satisfied and/or
(b) conferring
on a person or a body a function of determining, or a power to determine, when
the requirement is taken to be satisfied.[107]
The Explanatory Memorandum states:
Conditions may include closure criteria and metrics that the
holder of the authority must meet over a period of time; and documents and
reports that the authority holder is required to provide relating to Ranger’s
performance against those criteria and metrics ...
Section 41CH allows a Part III Authority to set out a more
detailed assessment process by which the Minister, and specified others [for
example, the Supervising Authority and/or Supervising Scientist] will determine
when the rehabilitation requirements can be taken to be satisfied.[108]
The Explanatory Memorandum notes that this would ‘provide
stakeholders with greater certainty about the pathway to Ranger’s eventual
close-out’.[109]
Proposed section 41CI provides for the Minister to
make a declaration that a Part III authority, or specified provisions of a Part
III authority, is no longer in force in relation to the whole, or a specified
part, of the land in the Ranger Project Area. The Minister may only do so if:
- the
rehabilitation requirements for the relevant area have been satisfied
- the
holder of the Part III authority agrees to the Minister making the declaration
- the
Minister has consulted with the Land Council.[110]
The Minister must provide copies of a declaration to the
holder of the authority, the Land Council, the Minister for the Environment,
and the NT Mining Minister.[111]
A declaration may have the effect of terminating the Part III authority.[112]
The Explanatory Memorandum notes that this corresponds to ‘Final Close-out in
the ERs [Environmental Requirements]’.[113]
Variation
and revocation of Part III authorities
Item 18 also inserts a new Division 4 into Part
III, with proposed sections 41CJ to 41CS.
Proposed section 41CS provides that the Minister
may only exercise their power to vary or revoke a Part III authority in a
manner that is consistent with the Commonwealth’s obligations under a s.44
Agreement under the ARLA, as they apply to the RPA.
Varying a
Part III authority
Proposed section 41CJ provides that a Part III
authority may only be varied in accordance with proposed section 41CK,
or a provision of an authority that provides for the authority to be varied.
Proposed section 41CK provides four circumstances
in which the Minister may vary a Part III authority:
- the
authority holder has failed to comply with a condition, restriction or requirement
of the authority and the Minister considers that the proposed variation is an
appropriate response to that failure (this replicates existing subsection
41A(4))
- to
extend the period in which the authority is in force
- the
Minister considers a variation necessary to ensure the continued effective
operation of the authority (for example, to make technical, operative and
administrative variations)
- to
include new conditions which describe when the requirements imposed by the
authority are taken to be satisfied (that is, close-out conditions).
Proposed section 41CL provides that the Minister
may only vary a Part III authority if a s.44 Agreement under the ALRA is
in force. Proposed sections 41CM and 41CN provide consultation and
notice requirements, ensuring that the Minister consults with the holder of a
Part III authority (that is, ERA), the Land Council, and the Minister for the
Environment before making a variation and gives notice of the variation to
these stakeholders—and the NT Mining Minister—after making a variation.
Proposed section 41CO provides limits on the time
periods within which the Minister may vary a Part III authority. The
Explanatory Memorandum explains:
This is consistent with the broader need to maintain
certainty of Ranger’s regulatory framework and allow the Minister to vary an
authority only in necessary, specified circumstances.[114]
Notably, proposed subsection 41CO(2) provides that
the Minister may vary a section 41 Authority where the holder has applied for
the authority to be varied, but fails to agree—or delays agreeing—to the
proposed terms of that authority within a reasonable period. Additionally, proposed
subsections 41CO(3) and 41CO(4) ‘prevent the Minister from extending the
Rehabilitation Authority unless the holder of the authority has failed to apply
for a further Rehabilitation Authority within the applicable timeframe or has
applied ... but failed to agree the proposed terms of that authority within a
reasonable period’.[115]
Reasonable period is not defined, with the Explanatory Memorandum noting this
is intended to ‘retain flexibility’.[116]
Revoking a Part III authority
Proposed section 41CQ provides that a section 41 Authority
may only be revoked in accordance with existing section 41C or proposed
section 41CR, or—for a Part III authority—a provision of an
authority that provides for the authority to be revoked.
Proposed paragraph 41CR(1)(b) provides that the
Minister may revoke a section 41 Authority if satisfied that the authority
holder has:
complied with any conditions or restrictions to which the
authority is subject, and any requirements imposed by the authority, that
relate to the protection, rehabilitation, remediation or monitoring of the land
in the Ranger Project Area.[117]
Remaining provisions of proposed section 41CR
require the Minister to consult with the Land Council before revoking an
authority, and give a copy of the instrument of revocation to the authority
holder, Land Council, Minister for the Environment and the NT Mining Minister.
Exemption
from Part 3 of the Environment Protection and Biodiversity Conservation Act
1999
Item 18 also inserts a new Division 5 into Part
III, covering a range of other matters. Notably, proposed section 41CW clarifies
that Part 3 of the EPBC
Act—which relates to requirements for environmental approvals under the
EPBC Act—does not apply to:
(a) actions
authorized by the historic section 41 authority or by a rehabilitation
authority; or
(b) actions
that a person has the power to perform under section 41 or 41CC of this Act
because such an authority is in force.[118]
Division 1 of Part 3 of the EPBC Act sets out the
requirements for approval of activities that have, will have or are likely to
have a significant
impact on matters of
national environmental significance. These include nuclear actions—including
rehabilitating an area used for uranium mining (Subdivision E)—as well as world
heritage, national heritage, wetlands of international importance, and listed
threatened species or endangered communities.
Proposed subsection 41CW(2) clarifies that
subsection 41CW(1) only applies to actions that are taken in accordance with
the relevant Part III authority. This mirrors language that is used for example
in the existing exemption for approvals under Part 3 of the EPBC Act for
Regional Forest Agreement (RFA) forestry operations, where those operations are
undertaken in accordance with the relevant RFA.[119]
The Explanatory Memorandum notes that ‘the section also
has the effect that Part 7–9 of the EPBC Act would not be engaged’.[120]
This means that a separate assessment and approval of proposed rehabilitation
activities that may have a significant impact on matters of national
environmental significance would not be required. The Explanatory Memorandum notes:
Ranger was approved based on the recommendations of the
Ranger Uranium Environmental Inquiry, which considered the environmental
impacts of proposed activities throughout 1975–1977 pursuant to the
now-repealed Environment Protection (Impact of Proposals) Act 1974. The
environmental conditions and requirements applying at Ranger are set out in the
historic Section 41 Authority which has been in force since 1999.
The regulatory framework applying to Ranger ensures the
rehabilitation continues to undergo assessment by the Commonwealth and NT
governments, informed by the independent advice of the Supervising Scientist
with input from Traditional Owner representative bodies. Rehabilitation is also
subject to ongoing monitoring and verification undertaken by the Supervising
Scientist.[121]
Replacement
of offence provisions
Items 20 and 21 repeal and replace existing offence
provisions relating to a refusal or failure to comply with a condition or
restriction of a Part III authority or a requirement imposed on the person by a
Part III authority (proposed subsections 41D(1) and 41D(2)).
The penalties for these offences—20 penalty units ($4,440)
for a person and 100 penalty units ($22,220) for a body corporate —appear to be
insubstantial and are significantly less than similar offences under the EPBC
Act.[122]
Part 2 –
Application provisions
Item 25 clarifies that proposed amendments to the
Act would apply in relation to a Part III authority whether the authority came
into force before, on or after the commencement of the proposed amendments.
Item 26 similarly clarifies that the offence
provisions in amended subsections 41D(1) and (2)—in relation to breach
of a condition, restriction or requirement—apply in relation to:
- acts
or omissions that occur on or after the commencement of the proposed amendments
and
- Part
III authorities that came into force before, on or after the commencement of
the proposed amendments.
Concluding comments
The Bill seeks to ensure that ERA continues to be bound by
an appropriate authority requiring it to rehabilitate the Ranger Project Area
in accordance with the Environmental Requirements, while allowing some
flexibility with regard to the date at which rehabilitation activities (but not
full restoration of the ecosystem) will be completed. The Minister has substantial
discretion at key junctures, including in deciding to pursue variation of the historic
section 41 Authority in the event that ERA does not apply for a
rehabilitation authority under Part III, determining (or making minor
modifications to) the Environmental Requirements, and with regard to key
timeframes.
There appears to be a significant shortfall in financial
provisioning for rehabilitation activities. This poses the consequent risk that
required works may not be completed. The Bill does not engage with issues of
corporate responsibility in the event that ERA (or its successors) are unable
to meet its obligations.
Appendix: Other uranium mines and prospects in the
Alligator Rivers Region, and rehabilitation status
Mine |
Date closed |
Rehabilitation status |
Ranger 3 Deeps (exploratory underground drilling,
including a $120m exploration decline)[123] |
Ceased June 2015 |
August 2021: backfill works completed; decline and vent
shaft backfilled 350 metres with waste rock, and capped with 10 metres of
concrete and waste rock |
Jabiluka[124]
|
1999
|
Mine did not commence commercial operation; remains under
long-term care and maintenance
2003: backfill of decline
2013: rehabilitation of interim water management pond
2005–2015: revegetation of site
|
Rum Jungle[125]
|
1971
|
1983–1986: rehabilitation works at a cost of $18.6m
2009: further works commence after earlier works found to
have deteriorated
2022: further rehabilitation works commence and are
expected to take 15 years at a cost of $300m
|
Narbarlek[126] |
Mining occurred over 4 months in 1979, with stockpiled ore
progressively processed until 1988 |
1998: rehabilitation activities commenced, but regulatory release
has not occurred |
South Alligator River Mines[127] |
1950s–1970s |
2006–2009: rehabilitation works funded and completed by
Australian Government |