|
House of Representatives Public Works
Navigation: Previous Page | Contents | Next Page
Chapter 3 Issues and Conclusions
Need
3.1
According to DFAT, while the apartments have been well maintained over
their 17 year life span, routine wear and tear has taken its toll on surfaces,
fixtures and fittings. The submission lists the following specific issues
which require addressing:
n bench and fixture
heights, which were based on Japanese standards, require redesign;
n services access doors
off corridors require fire rating in order to fully isolate shaft from
apartment spaces;
n inadequate drainage
in bathrooms;
n stairs and handrails
in stairwells need to be upgraded to meet current standards;
n inadequate sound
proofing between apartments;
n removal of asbestos
from bathrooms and terrace balcony under-surfaces throughout the apartment
blocks;
n upgrades to power and
data reticulation, electrical and fire detection infrastructure, engineering
services access and air reticulation;
n OH&S concerns,
particularly in relation to fire, electrical and ventilation require
addressing; and
n amalgamation of some
of the apartments to meet new requirements.[1]
Bench and Fixture Heights
3.2
The Committee questioned the Department as to the rationale for initially
designing bench and fixture heights to Japanese standards. The Committee was concerned that had the benches originally been designed with Australian occupancy
in mind, then fixtures and benches would not now require redesign.[2]
3.3
DFAT responded that the Japanese standards, which were utilised in the
construction of the apartments, do comply with Australian standards. However,
practical occupation of the apartments has highlighted the deficiencies in the
design of fixture and bench heights.[3]
3.4
The Committee sought assurances that, given the high number of overseas
properties that had recently been before it; that the issue of fixture and
bench heights was addressed in the design of those works. The Department
assured the Committee that
…those projects certainly have been built to the Australian
Standards and do meet the norm in Australia.[4]
Asbestos
3.5
Given that the building was occupied in 1990 and constructed in the late
eighties, the Committee was surprised to find that asbestos had been discovered
in the complex. The Department responded that once the issue had been brought to
its attention, investigations had revealed that it was not against Japanese
standards to use the asbestos sheeting which had been discovered.[5]
3.6
During the confidential hearing the Committee heard that the asbestos is
in the form of sealed hardboard. Asbestos had been discovered in the car park
basement area, and in some of the wet areas of the apartments and the balcony
areas. Further, the Department stated that the asbestos which had been found
in the car park had already been removed, and that the refurbishment works
presented an opportunity to remove the asbestos sheeting from the apartments.
The Department added that while the asbestos was in its sheeting form it
presented no danger, but that there was always a risk that it could be broken.[6]
Codes and Standards
3.7
DFAT submitted that the works would comply with current Japanese
building regulations and relevant Building Code of Australia (BCA) requirements
and that the works will comply with current Occupational Health and Safety
(OH&S) regulations.[7]
3.8
The Committee sought an explanation as to the extent of the OH&S
upgrades; in particular works relating to fire, electrical and ventilation
upgrades, that the works would entail.[8]
3.9
The Department responded that with regard to fire upgrades, it would be
installing a second method of egress from the apartments which was required so
as to comply with Japanese standards. The Committee sought clarification as to
what form the additional egress would take, and heard that it would be a
harness mechanism from the external balconies. According to DFAT, these
systems are specified and approved by the fire department in Tokyo.[9]
3.10
DFAT added that the building was originally constructed to the highest
seismic standards, and that it still meets the local codes. Further, the
emergency procedures for the building are ‘finely calibrated and practiced’ for
the sorts of crises that the Tokyo location may present.[10]
3.11
The Committee heard that the ventilation upgrades were to satisfy the
Japanese requirement that air is cycled through the apartments every two
hours. The electrical upgrades would improve services to meet current
standards,[11] including the number of
power points available throughout the apartments and reticulation of data and
television outlets.[12]
3.12
The Committee questioned the Department about the provision of wireless
broadband within the complex in order to save on the expense of cabling. The
Department responded that the advice from the local technician had been that it
would be beneficial to hardwire in the first instance. In addition, the
cabling was a combined voice data system, which had to be done through
hardwiring.[13]
Drainage
3.13
The Committee enquired as to the challenges that DFAT faced regarding
drainage issues in the apartments. The Department responded that the drainage
systems under the baths had a collection mechanism under the bath from where
the water finds its way into the pipes and runs away. Problems had arisen, due
to the lack of filtration, where the system would become clogged and overflow.
This system would be upgraded to deal with the drainage issues of the
apartments.[14]
3.14
Further clarification was sought as to whether these drainage problems
had impacted on the integrity of the base building. DFAT responded that no
structural damage had been detected and that it was more of an issue of
hygiene, convenience and damage to soft furnishings.[15]
Scope
Amalgamation of Apartments
3.15
The Committee sought clarification from the Department on the rationale
for amalgamating some of the apartments. DFAT explained the reason for this
was that some of the smaller two bedroom apartments were no longer being fully
utilised. The current project offered the opportunity to amalgamate units not
being fully utilised into larger apartments that could accommodate accompanied
officers. This was consistent with changes to staffing profiles at Australian
posts abroad, where the trend was toward fewer unaccompanied junior officers,
and more senior staff with accompanying family.[16]
The Committee heard that once the amalgamations were completed, there would be
no two bedroom apartments left on the embassy complex.[17]
Furniture Replacement
3.16
During the confidential hearing, the Committee questioned the
replacement of furniture and whitegoods. The Department responded that only
items that were built in would be replaced. Other furniture and whitegoods had
been well maintained and would therefore not be replaced.[18]
Tender Process
3.17
The Committee sought additional information as to the tender process and
how it would be managed. The Department responded that once the works had
received Parliamentary approval it would engage in a public tender process to
appoint the various consultants. In addition, the process would be competitive
and subject to the normal probity requirements, and would be advertised in Australia and Japan in order to give opportunities for Australian participation.[19]
Project Delivery
3.18
The Committee made enquiries about how the department would manage the
temporary relocation of staff while the works were being completed. The
department responded that is was looking at leasing approximately six
apartments for temporary relocation of families while work was being undertaken.
DFAT stated that it had been informed that this was the most efficient and cost
effective way of managing the project.[20]
Prototype Apartment
3.19
DFAT submitted that a prototype apartment – number 421 – had been
refurbished to evaluate the finishes, test feasibility assumptions, assess
unknown factors, ascertain the time and cost of the works, identify likely
problems and solutions and establish a quality benchmark for all apartments.[21]
3.20
The Committee sought clarification as to how the costs of the prototype
apartment had been met. DFAT responded that it allocated funds from the
Overseas Property Office (OPO) budget to pay for this type of development
activity. The Department added that the development of the prototype allowed
it
…to be better educated and more accurate in the development
of the costings for the overall project delivery.[22]
Operation of the Overseas Property Office (OPO)
3.21
At the confidential hearing, the Committee questioned officers from DFAT
about the operation of the OPO. The Committee heard that the OPO charter is to
operate the overseas estate on a commercial basis and as such it seeks to have
fully commercial rents on the properties. The commercial arrangement places a
commercial framework around the relationship that the OPO has with other
agencies, and allows the properties to be managed in a commercial way.[23]
3.22
The Committee explored what, if any, parliamentary scrutiny was
exercised on the OPO. The Department stated that its works go through the
portfolio budget statements, are audited by the Australian National Audit
Office (ANAO) and are also reported in the DFAT annual report.[24]
Cost
3.23
The Committee heard that the value of the chancery complex in Tokyo was $286.7 million as at 30 June 2007. DFAT added that the remaining useful life of
the complex, subject to mid-life refurbishment and ongoing maintenance, is at
least 35 years. As a consequence, DFAT argued that the projected out-turn cost
of $22 million represents a good investment.[25]
Recommendation 1
|
|
The Committee recommends that the proposed refurbishment of
staff apartments, Australian embassy complex, Tokyo, Japan proceeds at an estimated cost of $22 million.
|
Hon Judi Moylan MP
Chair
9 October 2007