Chapter 3 Issues and Conclusions
Need
3.1
According to Defences’ submission to the Committee the need for this
project arises predominantly from the need to replace and refurbish a number of
facilities at RAAF Base Pearce that are ageing, substandard, and do not comply
with current building standards.[1]
3.2
In addition a number of new facilities will be provided that will
assimilate new technologies, including aircraft types, so as to ensure that the
base is able to support future operations.
3.3
During the course of the site inspection, the Committee assessed the
standards of those facilities that are the subject of either refurbishment or
demolition, and agreed that the description applied to them by Defence was reflected
in the state of the facilities.
3.4
A case in point was the proposal to construct a new base fuel farm in
order to replace the current non-compliant facility. Defence informed the
Committee that the existing fuel farm had been built at a time when codes and
building standards were not as stringent as they are today. While the
department had no issue with the integrity of the current facility, the fuel
tanks did not meet the current Australian standards that were formulated to
eliminate the great majority of potential risks. Against this background, Defence
was of the view that it was incumbent on the department to ensure the integrity
of fuel storage facilities through the provision of a new fuel farm that would
meet these standards.[2]
3.5
During the site inspection, Defence explained that the proposed new fuel
farm would be relocated to a site located away from the flight path and the
former fuel storage site remediated, including the removal of soil
contamination and re-grassing.
Heritage Issues
3.6
Leading on from the matter of need, the Committee inquired as to the
criteria employed by Defence in reaching a decision as to whether to retain a
building or deciding to demolish it. Defence responded that decisions as to
whether to retain or demolish a building were based on the department’s
heritage assessors who provide a report as to the heritage value of each of the
buildings.
3.7
Defence explained during the course of the confidential hearing that:
The base cinema was built in the early thirties. The transit
rooms were an accommodation building built in the early thirties and are
evident in Air Force bases all over Australia, whereas the cinema or something
like that might not be. Our experts and our consultants looked at the function
and whether there are others existing … elsewhere on the base or on other
defence land. Then an assessment was made of whether these were of high,
medium or low significance.
3.8
Defence also stated that following on from the Committee’s recommendations
associated with works proposed for Lavarack Redevelopment Stage 4, the
department had written to the Department of Environment and Water Resources
(DEWR) seeking guidance on the Defence management plan for RAAF Base Pearce. [3]
The outcome of this process was that DEWR had undertaken an assessment of
buildings to be demolished against the Commonwealth Heritage List criteria but indicated
that Defence would need to ensure that buildings scheduled for demolition be
recorded and passed to DEWR for archiving.
Recommendation 1 |
|
The Committee recommends that in due course the Department
of Defence provide details of heritage buildings demolished and referred for
archiving to the Department of Environment and Water Resources. |
The Tender Process
3.9
Defence has stated that the delivery of the works will be via a managing
contractor with responsibility to control and coordinate concurrent design and
construction of the various elements of the project, and maintain a schedule to
this end.[4] A project manager will
also be appointed to act as the contract administrator to the managing
contractor for the delivery phase of the project.[5]
3.10
The Committee inquired as to the processes Defence had followed with
regard to the tendering processes for these two appointments.
3.11
In responding, Defence informed the Committee that Sinclair Knight Mertz was selected as the project manager/contract administrator and John Holland as the managing contractor for the development phase of the contract. For the
procurement of the managing contractor, Defence employed a two-stage open
tender process from which three nationally based companies were short-listed
for the second stage of the tender process. According to Defence:
All three companies submitted a tender for the work and John Holland was selected as the best value for money for the Commonwealth for the development
of the project.[6]
3.12
In further elaboration, the department informed the Committee that an
average of costs had been prepared, and all of the tenders came within the
range of that average.[7]
3.13
The department also stated that independent of cost, the technical merit
of tenders were assessed adding another tier to the selection of tenderers
reinforcing the best value for money to the Commonwealth.[8]
The Noise Attenuated Engine Run-up Facility
3.14
In its Statement of Evidence, Defence states that it proposes to provide
a new purpose built engine run up facility that meets OH&S regulations and
noise pollution requirements. The engine run up procedures are required to be
performed as part of aircraft maintenance checks and adjustments.[9]
3.15
At the Hearing, the Committee sought further details of this facility,
particularly as to how the new proposed facility would improve the present
situation.[10]
3.16
The department informed the Committee that RAAF Base Pearce has a
requirement to conduct testing of aircraft engines after maintenance.
Currently this testing is conducted on an open concrete slab located in
proximity to the base boundary. According to Defence the engine testing
process involves OH&S issues requiring maintenance staff to wear personal
protection equipment (PPE) as protection against noise damage.[11]
3.17
The proposed new facility includes a purpose built building that will
considerably reduce noise pollution. In addition to PPE to minimise noise
levels for maintenance personnel, a sound attenuator protection booth will be included
as part of the development to further reduce exposure to noise levels. The new
facility will reduce noise levels both on site as well as reducing noise
emissions from the base to adjacent properties.[12]
3.18
The Committee asked the department whether it had an indication of the
known percentage reduction or an approximation of a percentage reduction in
sound emissions.
3.19
The Committee was informed that a noise modelling report was undertaken
in December 2006, with a further field study undertaken in May 2007. The results
of both the report and the field study demonstrated that noise levels were in
excess of the Western Australian Environmental Protection Authority guidelines.
These outcomes were used in the design of the new facility with the objective
of achieving a reduction in noise emissions by 24 decibels to make it compliant
with Western Australian regulations.[13]
Air Movements Terminal
3.20
The department proposes to upgrade the air movements terminal by
providing new office facilities and staff amenities, and new passenger
facilities. A proposed extension to the building will remove administrative
and passenger functions from the existing cargo hanger, returning it to its
intended function.[14]
3.21
The Committee sought additional information regarding passenger
movements during peak load times. In responding Defence stated that the
proposed works would allow for future operations that accompany new aircraft
types and the potential increase in passenger numbers arriving and departing
from the facility. According to Defence:
Flights coming in are not necessarily limited to single
aircraft movements at one time. We have the capacity in that area to put at
least three C130s in close proximity to each other ….So certainly the capacity
would be in the area of several hundred people at any one time.[15]
3.22
The Committee inquired as to the nature of arrangements regarding an Australian
Quarantine Inspection Service (AQIS) and Customs presence to process incoming
personnel from overseas. The current arrangement as explained by Defence was
to contact these agencies in advance of arrivals of personnel from overseas who
then attend on an ‘as required basis’.[16]
Water and Energy
3.23
Under the heading ‘Energy Conservation Measures and Ecologically Sustainable
Design’ in its submission, Defence mentions at paragraph 64 (g) that it
proposes to install waterless urinals and water efficient fixtures. There is
no other reference to water conservation and other issues of water
sustainability on the base.
3.24
The Committee sought an expanded explanation from Defence as to (a) current
issues affecting the delivery of water to RAAF Base Pearce, and (b) what
consideration had been given to water storage for fire fighting and irrigation,
noting that this was currently sourced from the potable water supply.[17]
Water Infrastructure Issues
3.25
In regards to the delivery of water to RAAF Base Pearce, Defence
informed the Committee that water is delivered by way of an aquifer located
approximately 3.5 kilometres from the base from where it is pumped to a main
water storage tank on the estate. From there, it is gravity fed to potable
water tanks located at various sites throughout the base.[18]
3.26
The department commented that it has significant concerns over the age
of the current system, now some 70 years old. Defence indicated to the
Committee that the water supply to the base was compromised due to a number of
problems that include:
n no filtration system
for potable water;
n the existing water
main being made up of a mix of cement lined cast iron pipe from the thirties,
asbestos pipe and PVC pipe;
n untreated water
contamination of the potable water system; and
n chlorination levels
not being maintained to a level that would meet the Australian Drinking Water
guidelines, leading to the supply being shut-down in early 2007.[19]
3.27
In response to the problems currently being experienced, Defence advised
the Committee that:
Due to the current water quality concerns, the base has
stopped personnel drinking water from the base’s potable water supply.[20]
3.28
As a result of the closure of the system, Defence ‘fast tracked
negotiations’ with the Western Australia Water Corporation to provide a potable
water supply from their system to the Chittering Road tanks and a 50mm supply
line to Pearce to provide a separate potable water supply. This is currently
under investigation by the Water Corporation to determine the scope of works
required to return the base supply to potable water quality. However,
according to Defence, it will not be possible to return the supply to a
standard that complies with the Australian Drinking Water Guidelines until the
current redevelopment proposal has been completed and all potable water mains
on the base have been replaced.[21]
3.29
With specific reference to the matter of irrigation and fire fighting
water, Defence explained that as part of the redevelopment, water delivery will
be split between potable water and non-potable water that will be used for
irrigation. In addition captured rainwater from roof structures will be used
for toilet flushing in LIA.[22]
3.30
The issue of water was also raised by Mr David Lombardo, Vice-President
of the Bullsbrook and Chittering Chamber of Commerce. In evidence before the
Committee, Mr Lombardo, noting the possibility of RAAF Base Pearce being
connected to the Bullsbrook town water supply, requested that in negotiations
with the Western Australia Water Corporation the Chamber and local government
also be involved.[23]
3.31
In responding the Committee made note that the issue of water and its
implications for other critical infrastructure development was of concern along
the Great Northern Highway corridor, and asked whether the Chamber had any
suggestions as to how the current water shortage might be addressed.[24]
3.32
In responding, the Chamber explained that the Pearce area was at the
most northern end of the Water Corporation infrastructure and that it had
limitations in meeting the demand of local communities. The capacity to
deliver water in sufficient quantity would be further impacted by the growth of
Bullsbrook and the demands of the RAAF. The Chamber informed the Committee of
the Water Corporation’s preliminary plans that would involve a mains extension
that would possibly alleviate the current situation, but in the meantime the supply
of water should take into account the future demand of the township of Bullsbrook as well as those of Pearce.[25]
Water Harvesting
3.33
The Committee was also interested in following-up the extent to which
Defence had invested in rainwater harvesting from roof structures and the
extent to which collected rainwater could be used at the base messing facility
and other water requirements.[26]
3.34
Defence responded that rainwater tanks would be used in delivering water
to the mess as well as to LIA accommodation. This would take the form of cold
water connections and toilet flushing. Defence also mentioned that appliances,
including dishwashers, washing machines and other devices, would be selected on
the basis of low water consumption. In the case of shower heads these would be
AAA compliant. In addition, the extent of the irrigation network will be
significantly reduced resulting in potential savings in water usage.[27]
3.35
According to Defence, in 2006 the amount of potable water used on base for
all purposes – irrigation, washing, drying, potable and non potable use - was
of the order of 107 mega litres, or about 1½
days use for Canberra.[28]
3.36
However Defence could not provide an estimate of the potential water
usage following the completion of the redevelopment works, although the
department did suggest that it would decrease once the water infrastructure and
irrigation systems had been redeveloped. Defence accepted that there is
significant water wastage due to systems failures and the need for system
flushing being required each time the water main fails.[29]
3.37
The department informed the Committee that it had commissioned an
Environmental Sustainable Development Report to assess what measures should be
implemented to reduce water use so as to meet government policy. The Committee
indicated that it would be useful if Defence could provide documentation on the
total extent of initiatives proposed to improve water efficiency.[30]
Recommendation 2 |
|
The Committee recommends that Defence provide advice to
satisfy the Committee that everything is being done to capture and use water
on RAAF Base Pearce in view of community concerns related to water availability. |
Energy
3.38
The Committee congratulated Defence in addressing energy conservation
issues, noting the department’s comment at paragraph 63 of its main submission
that:
Defence reports annually to Parliament on its energy
management performance and on its progress in meeting the energy efficiency
targets established by Government as part of its commitment to improve
Ecologically Sustainable Development.
3.39
In the context of the current project, Defence informed the Committee
that the department had discussed water and energy efficiency measures with the
Australian Greenhouse Office (AGO). It stated that all appliances and lighting
would reflect the guidelines of the AGO applicable to energy and water use.[31]
Consultations
3.40
The department states in its Statement of Evidence that:
Discussions have been held or will be held with the Federal
Member for Pearce, Local Members of the City of Swan and the Chittering Chamber
of Commerce, the Western Australian Water Corporation, the Department of
Environment and Water Resources, and the Department of Conservation and Land
Management, Western Australia.[32]
3.41
That noted, there was no evidence available from Defence on the scope of
the consultations that had either occurred or were mooted. From evidence
presented to the Committee by the Bullsbrook and Chittering Chamber of
Commerce, the Committee is aware of local concerns, particularly regarding
delivery of water through the Western Australian Water Corporation
infrastructure, and the pressures on the availability of water to the local
community.
3.42
The Committee notes that there does not appear to be any consultations
scheduled to take place with the local fire authority, particularly as regards
any design works that might be required in the event of an incident requiring
the participation of local brigades.
3.43
It would assist the Committee if the department would furnish it with
advice as to the progress on the consultative process, with particular
reference to any aspects that have a bearing on the final design works
associated with the redevelopment of the base.
Recommendation 3 |
|
The Committee recommends that Defence continue to pursue
consultations with appropriate local, State and Federal government agencies
particularly on the delivery of water to the site, having regard to local
community interests, and that it consult with the local fire authority on
appropriate fire regulations that might need to be incorporated into the
design of the works. |
Project Costs
3.44
The department’s Statement of Evidence puts the estimated out-turn cost
for this project at $142.2 million including:
n all planning,
management and design fees;
n construction costs;
n furniture and
fit-out; and
n equipment and
contingencies.
3.45
Construction is scheduled to commence in 2007 with a completion by 2011.[33]
Recommendation 4 |
|
The Committee recommends that RAAF Base Pearce Redevelopment
Stage 1 proceeds at an estimated out-turn cost of $142.2 million. |
The
Hon Judi Moylan, MP
Chair
9 August 2007