Chapter 3 The Proposed Works
Purpose
3.1
The purpose of the proposed works is to relocate the Land Engineering
Agency (LEA) Test Services from Defence Site Maribyrnong (DSM) to the
Monegeetta Proving Ground. The Maribyrnong site has been identified as surplus
to Defence and Commonwealth Government requirements and is to be disposed of
once all units currently located at the site have been relocated, which in the
case of LEA, will be following construction on the site at Monegeetta.[1]
Need
3.2
The need for the proposed works arises from the decision to dispose of
the former site used by the LEA at Maribyrnong, and the opportunity to locate
the LEA at one site rather than two which has previously been the case.
Further, the relocation of the LEA from its former site in Maribyrnong will
hasten the disposal of the DSM property when works at Monegeetta have been
completed.[2]
Scope
3.3
Defence submitted that the proposed works will include new facilities;
refurbishment of existing facilities; and upgrade to site infrastructure.
New Facilities
3.4
New facilities include:
n construction of a new
Enclosed Light Armaments Facility (ELAF) to accommodate LCS functions. The
ELAF will provide floor space of approximately 920 square metres including:
- a
magazine and armoury; and
- two fully
enclosed firing tunnels (25 metres long and 100 metres long).
n construction of a new
laboratory, workshop, and administration building of approximately 4,730 square
metres to support Accredited Test Services (ATS) functions. This building will
include:
- an Electronic
and Communications Laboratory (ECL) providing: Electro-Optics capability; Electro-Magnetic
Compatibility chambers; and Electrical Testing and Calibration; and
- a
Mechanical and Environmental Laboratory (MEL) providing: large climatic
chamber; large cold chamber; small climatic chambers; mechanical calibration
facility; heavy vibration test facility; and static and dynamic displacement
and force measurement testing facility; and driving rain simulation facility.
n construction of a new
Petrols, Oils and Lubricants (POL) store.[3]
Refurbishment of Existing Facilities
3.5
Modifications to the existing headquarters building includes:
n accommodating new
communications and security facilities; and
n providing disabled
access through construction of a new ramp and entry.[4]
Site Infrastructure Upgrade
3.6
The existing site infrastructure requires upgrade to support the
additional facilities. The infrastructure works includes:
n a minor upgrade of
the storm water and sewer services;
n separating the
domestic water supply to provide a dedicated fire service as required by the
Country Fire Authority;
n installing a new
substation to meet the increased power demand;
n constructing roads to
new buildings; and
n landscaping.[5]
Project Delivery
3.7
A head contract delivery system is proposed for this project. According
to Defence, this form of delivery is particularly well suited to projects where
the scope is well defined and works can be constructed unhindered by
operational constraints. Specialist sub-contractors will be identified for the
supply of specialised equipment.[6]
3.8
A project manager has been appointed to represent Defence and act as
contract administrator for development of the project. A designer has been
appointed to prepare designs and, subject to parliamentary clearance of the
project, will finalise the design documentation and undertake inspection
services during the construction phase.[7]