Chapter 5 Enhanced Land Force
Stage 2 Facilities Project
5.1
The Enhanced Land Force Stage 2 (ELF 2) facilities project proposes to construct
new, extended or refurbished facilities at Gallipoli Barracks, Enoggera,
Queensland and other defence bases and training areas. The estimated cost of
the project is $1,457.836 million (excluding GST).[1]
5.2
The proposal was referred to the Committee on 17 September 2009.
Conduct of the inquiry
5.3
The inquiry was advertised in local and national newspapers and
submissions sought from those with a direct interest in the project. The
Committee received eleven submissions and five supplementary submissions, one
of which was confidential and detailed the project costs. A list of submissions
can be found at Appendix A.
5.4
The Committee undertook a site inspection of Gallipoli Barracks followed
by a public hearing and an in-camera hearing on the project costs on Wednesday,
4 November 2009 in Brisbane, Qld. In addition, the Committee undertook two site
inspections, to Lone Pine Barracks, Singleton, NSW on Friday, 30 October 2009
and Lavarack Barracks, Townsville, Qld on Thursday, 5 November 2009.
5.5
The transcript of the public hearing as well as the submissions to the
inquiry are available on the Committee’s website.[2]
Plans for the proposed works are detailed in Submission 1: Department of
Defence (Defence).
Need for works
5.6
The Defence submission states that the proposed works are needed due to
the ELF initiative which aims to increase the size of the Defence force by
3,000 members. The works are the second stage of the ELF stage 1 project which
was approved by the Committee in February 2009. Both projects are required in
order to support the increased capacity of the Defence force which will result
from the ELF initiative.
5.7
On 2 October 2007, the Government announced the re-raising of the 8th/9th
Battalion to be located at Gallipoli Barracks, Enoggera and deployable by 2010.
This requires the development of permanent facilities and infrastructure to
support:
n 8th/9th
Battalion, Royal Australian Regiment and other elements of 7th
Brigade and 1st Division being enhanced under this project at
Gallipoli Barracks; and
n the development of
enabling capabilities, in order to sustain increases in the delivery of collective
training capability, career training and logistic support facilities at Defence
Bases and Training Areas in South East Queensland and various locations
throughout Australia.
5.8
The Committee finds that there is a need for the proposed works.
Scope of works
5.9
The proposed scope of works is detailed in Submission 1: Department of
Defence. In short the project proposes the following by state.
QUEENSLAND
Gallipoli Barracks, Enoggera
n Elements to enable 8th/9th
Battalion and the growth in the supporting units to fit within a spatially
constrained Barracks:
§
construct new 8th/9th Battalion precinct
comprising Battalion headquarters and Training facilities, Manoeuvre Company
and Manoeuvre Support Company facilities and Administration Company facilities;
§
construct new 2nd Combat Engineer Regiment facilities
comprising Regimental Headquarters and Unit Training, 2, 7 and 11 Combat
Engineer Squadrons facilities, 24 Support Squadron facilities, Operations
Support Squadron facilities, Transport Compound and Training facilities;
§
construct new 7th Combat Signal Regiment precinct
comprising Regimental Headquarters and Unit Training, 139th and 140th
Signal Squadron facilities and Operational Support Squadron facilities;
§
construct new and refurbish existing 7th Combat
Services support Battalion facilities comprising shared two-storey facility,
Battalion Armoury workshop, Electronic Instrument Repair workshop, Vehicle
Storage Compound, Supply Company warehouse, extension of Vehicle Workshop, new
Bulk Fuel Tanker park and administration building;
§
construct new 2nd/14th Light Horse Regiment
facilities comprising working accommodation, storage space and ablutions;
§
construct new Headquarters for 1st Division and 1st
Intelligence Battalion comprising shared office building, Battalion Q-Store,
administration, ablutions and maintenance facility;
§
construct new multi-storey Explosive Hazards Centre;
§
construct new working accommodation, storage and vehicle shelters
for 1st Topographical Survey Squadron;
§
construct new facilities for Land Warfare Centre Warrant Officer and
Non Commissioned Officer Academy comprising lecture theatres, rooms, working
accommodation and living-in accommodation;
§
construct new Defence Support precinct comprising three-storey
office building and garrison conference centre;
§
construct new Garrison support precinct comprising facility for
Defence Publishing Service, Mail Centre and Furniture Store;
§
other various new facilities including Joint Logistics Unit – South
Queensland Clothing Store, three multi-storey car-parks, additional childcare
centre, Physical Training Centre comprising indoor pool, courts, rooms and
offices and 361 Living-In Accommodation rooms;
§
refurbish the DefCredit facility;
§
construct new and refurbish existing Barracks Training Facilities;
and
§
construct new and refurbish existing Engineering Services comprising
fire and potable water reticulation, stormwater, sewer, natural gas, high voltage
electrical reticulation, fire protection systems, communications networks, road
network and car-parking.
Lavarack Barracks, Townsville
n refurbish facilities
for the 3 Combat Services Supply Battalion;
n construct new and
refurbish existing Combat Training Centre;
n construct new and
refurbish existing Land Warfare Centre Warrant Officer and Non-Commissioned
Officer Academy;
n construct 3 new
ranges for the Field Training Area; and
n construct new Explosives
Store House.
Wide Bay Training Area, near Gympie
n construct new Special
Weapons Range, Assault Grenade Ranges, Explosive Pallet Space, Marksmanship
Training Range and Accommodation; and
n refurbish existing Vehicle
refuelling/washing facilities, Infrastructure and Demolitions Range.
RAAF Base Amberley, Ipswich
n construct new
facility to support the relocation of Headquarters 6th Engineer Support; and
n construct new facilities
to support a regiment from Gallipoli Barracks, Enoggera, Queensland comprising
working accommodation, ablution, storage and training facilities.
Greenbank Training Area, Greenbank
n construct new 25th/49th
Battalion Headquarters, 2 Company buildings, Q Store and transport compound;
n construct new accommodation
facilities;
n construct new
training facilities comprising Safe Driver Training Area, Marksmanship Training
Range, Range control complex, Urban Operation Training facility, Method of
Entry training facility, Engineer Mine Clearance Lanes and Vehicle wash
facility and depot; and
n construct new entry
point.
Kokoda Barracks and Canungra Training Area, Canungra
n construct new Battle
Simulation Centre, Living-In Accommodation and Camp Accommodation; and
n refurbish existing
facilities comprising works to the Gymnasium and Electronic Open Range.
NEW SOUTH WALES
Lone Pine Barracks, Singleton
n construct new School
of Infantry Headquarters, permanent Living in Accommodation, Battle Simulation
Centre, Weapon Repair Facility, Museum and Pass Office; and
n construct new and
refurbished training area and ranges comprising new Urban Operations Training
facility, new Explosive Pallet Space, new vehicle wash point and refurbished
ablutions and storage.
Garden Island and HMAS Penguin, Sydney
n construct new Primary
Casualty Reception Facility comprising Central Dispensing Point addition at
Garden Island; and
n refurbish existing working
and training facilities and HMAS Penguin.
AUSTRALIAN CAPITAL TERRITORITY
Royal Military College, Canberra
n construct new Living-In
Accommodation and working accommodation for instructors; and
n construct new facilities
for Majura Training Area Camp Blake comprising accommodation, lecture theatre,
headquarter offices, amenities and refurbishment of existing Urban Operations
Training Facility.
VICTORIA
Simpson Barracks, Watsonia
n construct new Technical
Training Wing building; and
n refurbish covered
training area.
Puckapunyal Military Area, Puckapunyal
n construct new Explosive
Pallet Space.
SOUTH AUSTRALIA
RAAF Base Edinburgh, Adelaide
n construct new Land
Warfare Centre’s Warrant Officer and Non-Commissioned Officer Academy.
Cultana Training Area, Cultana
n construct new
Explosive Pallet Space, Urban Operations Training facility, Field Firing
Training system Range and accommodation.
5.10
The ELF Stage 2 project is due to commence construction in mid 2010 with
completion anticipated in 2014.
5.11
The Committee finds that the proposed scope of works is suitable to meet
the needs of the ELF Stage 2 Facilities project.
Cost of works
5.12
The total estimated out-turn cost for this project is $1,457.836 million
excluding GST.
5.13
Defence notes in its submission that it anticipates an increase in net
operating costs due to the construction of new facilities and the associated
increases in facilities maintenance, cleaning and utilities expenses.[3]
5.14
The Committee is satisfied that the costings for the project provided to
it are adequate and suitable contingency planning is in place to ensure budget
overruns in any one area do not compromise the project as a whole.
Deferred works
5.15
Defence briefed the Committee on the potential for savings accrued
throughout the works project to be used to fund deferred works. In particular
two issues of concern were discussed, being:
n urgent upgrades that
may result from the Defence security review; and
n the lack of adequate
Living-In Accommodation at Townsville for personnel at Lavarack Barracks,
Townsville.
5.16
The Committee encourages Defence to ensure that any deferred works focus
on potential security upgrades to bases and the provision of Living-In
Accommodation at Lavarack Barracks, Townsville.
Recommendation 6 |
|
The Committee recommends that the Department of Defence
direct any savings identified in the Enhanced Land Force Stage 2 facilities
project on Lavarack Barracks towards improving base security and providing
additional Living-In Accommodation at Lavarack Barracks, Townsville.
|
Project issues
Traffic concerns
5.17
The most significant concern that has been raised with the Committee
relates to traffic congestion around a number of the bases where ELF 2 works
will occur. A number of submissions to the inquiry as well as participants at
the public hearing raised concerns about the severity of traffic congestion
around the various bases in Queensland. [4]
5.18
Specific traffic problems are detailed below.
Gallipoli Barracks
5.19
Local residents expressed dissatisfaction with the current levels of
traffic on roads surrounding the base, in particular Samford Road. Residents
stated that traffic congestion could be eased by building a new entrance to the
Barracks off Samford Road.[5] They assess that this
entrance would ease congestion on other local roads by drawing traffic away
from those areas.
5.20
Defence responded that there is land reserved for an entry on to Samford
Road and that consultation with state and local government is ongoing. Defence
added that it hoped to resolve this issue in the next six to 12 months.[6]
Recommendation 7 |
|
The Committee recommends that the Department of Defence
consult with state and local governments in order to finalise plans for an
entrance off Samford Road, Enoggera with Defence funding a fair and
reasonable portion of the cost of the road works, in order to ease traffic congestion
in the vicinity of Gallipoli Barracks.
|
Greenbank Training Area
5.21
Logan City Council raised concerns about the proposal to relocate the
range entry of the Greenbank Training Area. Of particular concern to the Council
was the impact of increased traffic and military convoys on Greenbank State
School, which would be directly impacted by the proposed changes.
5.22
Defence responded that the proposed new entry point was indicative only,
and that the final location was yet to be determined, and will be done once a
detailed traffic study has been undertaken. Defence undertook to consult with
Logan City Council and the Queensland Department of Transport and Main Roads in
the preparation of the traffic study. Defence added that Defence vehicles would
not be required to drive along Goodna Road past the Greenbank State School.[7]
Wide Bay Training Area
5.23
A submission to the inquiry raised concerns that there is only one
access road to Wide Bay Training Area. The submission states that there is a
proposal to upgrade Counter Road, which would provide an alternate access to
the training area, however the upgrade cannot commence due to a lack of
funding.[8]
5.24
The Committee recognises that solving traffic problems around Defence
bases is not only the responsibility of Defence. Nevertheless, as a contributor
to traffic congestion, Defence should accept responsibility for some of the
traffic concerns. The Committee urges Defence to consult with federal, state
and local traffic and roads authorities to mitigate some of the traffic
problems which have been raised throughout this inquiry.
5.25
Another concern that has been brought to the attention of the Committee,
in the current and previous inquiries, is the impact of anti-social and
dangerous behaviour by Defence personnel on the local communities in which
Defence bases are located. Similar concerns have been raised in Chapter 3. The
Committee remains concerned that the behaviour of some Defence force personnel
impacts negatively on local residents. Defence has a responsibility, as an
employer and member of the community, to ensure that its personnel act in a
responsible manner both on and off-base.
Consultation
5.26
The Committee acknowledges the difficulty confronting Defence when
trying to consult with multiple stakeholders, and also acknowledges the recent good
work of Defence in trying to ensure that it consults more widely.
5.27
However, as mentioned in the previous section, the Committee is aware of
significant community concerns about the proposed works, many of which have
resulted from the perceived inadequacy of Defence’s consultation process.
5.28
Members of the community were given the opportunity to raise their
concerns at the public hearing in Brisbane on 4 November 2009. These concerns
include a failure by Defence to consult with the local State Member of
Parliament, Mr Murray Watt MP, Member for Everton, whose electorate would be impacted
on by the proposed works on the Base. Mr Watt recommended that:
… in future local members whose electorates approach the
barracks be consulted, given that there are often spillover effects from the
barracks onto their electorates.[9]
5.29
The representative from Logan City Council, Mr James, raised the concerns
regarding the Greenbank State School as noted above. Mr James noted that the Council
would find it helpful if Defence consulted with the school directly to give
accurate information and respond directly to concerns of the school.[10]
5.30
The Committee is of the opinion that many community concerns about
Defence projects can be addressed and minimised through proper consultation. The
Committee agrees that it is incumbent on Defence to be proactive when
undertaking consultation by seeking to engage with all parties that may have an
interest, not simply those in the immediate vicinity of the works.
Recommendation 8 |
|
The Committee recommends that the Department of Defence
develop a consultation protocol that ensures that consultation with local government
and, where appropriate state government, occurs in line with routine local
planning procedures.
|
Open space
5.31
The Committee questioned Defence about the loss of open space at Duncan
Oval, Gallipoli Barracks as a result of the proposed works. The Base Commander
noted that the loss would be around 10 percent of current open space and that
while he:
… would rather not lose any ... that [the 10 percent loss]
will not have a significant impact on what we use it for now.[11]
5.32
Brigadier Grice from Defence’s Infrastructure Asset Development Branch
noted that potential existed in future works projects to expand the open spaces
of Gallipoli Barracks, and that this may result in a 15 percent increase in the
size of Duncan Oval based on its original size.[12]
5.33
The Committee is concerned about the impact of a loss of open space on
the training functions and physical exercise of Defence personnel based at
Gallipoli Barracks.
Recommendation 9 |
|
The Committee recommends that the Department of Defence
ensure that any future proposals for work at Gallipoli Barracks consider
increasing the size of Duncan Oval, with a view to increasing the open space
available on the Base.
|
Environmental Considerations
5.34
Defence submitted that a Departmental review of the project has not
identified any significant environmental concerns. The submission adds that the
designs have incorporated features such as: minimising tree loss through
prudent siting decisions, use of low-water indigenous vegetation and stormwater
reuse in gardens, and harnessing energy efficiency and conservation measures.
5.35
The Brisbane Region Environment Council (BREC) made a submission to the
Committee, and was represented by Mr Fensom at the public hearing. BREC raised
concerns about the impact on flora and fauna of elements of the project at
Greenbank Military Training Area and that environmental management plans had
not been developed to mitigate any potential negative environmental impacts.[13]
5.36
Defence responded that it is complying with the Environment
Protection and Biodiversity Act 1999 through developing a Defence
Environment Management System (EMS). This EMS manages the environmental values
across the site including weed control and fire management. In addition, the
works proposed for Greenbank Military Training Area will be governed by a
Construction and Environment Management Plan (CEMP). The CEMP will manage the
environment during construction and will also address off-site construction
impacts such as construction vehicle traffic and lighting.[14]
Committee comment
5.37
Overall, the Committee is satisfied that this project has merit in terms
of need, scope and cost.
5.38
Having examined the purpose, need, use, revenue and public value of the
work, the Committee considers that it is expedient that the proposed works
proceed.
Recommendation 10 |
|
The Committee recommends that the House of Representatives
resolve, pursuant to Section 18 (7) of the Public Works Committee Act
1969, that it is expedient to carry out the following proposed work:
Enhanced Land Force Stage 2 Facilities Project.
|